SOLAR · SOUTHEASTSolar project IC-1038, Ware County
Solar project IC-1038, Ware County is a 120 MW solar request suspended in the Southeast interconnection queue, in Ware County, Georgia, connecting to Southern Company.
Queue statusPaused / redesign
- PlanningQueued May 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- IC-1038
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Douglas - Kettle Creek Primary 230 kV Line
- Location
- Ware County, Georgia
- Technology
- Solar: 120 MW
- Total requested
- 120 MW
- Service type
- Energy only (ERIS)
- Queue status
- Suspended
- Entered queue
- 19 May 2022
- Proposed online date
- April 2026
Location
Marker shows the centre of Ware County; the queue data does not give exact sites.
Other requests in Ware County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem