United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

SOLAR Β· SOUTHEAST

Solar project IC-728, Ware County

Solar project IC-728, Ware County is a 124 MW solar request withdrawn in the Southeast interconnection queue, in Ware County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2018 (completed)
  2. Withdrawn / abandonedJun 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-728
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Homeland - Kettle Creek Primary 230 kV Line
Location
Ware County, Georgia
Technology
Solar: 124 MW
Total requested
124 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
21 August 2018
Withdrawn
June 2019

Location

Marker shows the centre of Ware County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Ware County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem