🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Tennessee

SOLAR · SOUTHEAST

Solar project 510, Carroll County

Solar project 510, Carroll County is a 140 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Carroll County, Tennessee, connecting to Tennessee Valley Authority.

Queue statusConsented
  1. PlanningQueued Jul 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
510
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Connection point (POI)
Huntingdon - Milan 161-kV TL
Location
Carroll County, Tennessee
Technology
Solar: 140 MW
Total requested
140 MW
Study phase
IA Executed
Queue status
Active
Entered queue
22 July 2022
Proposed online date
November 2029

Location

Marker shows the centre of Carroll County; the queue data does not give exact sites.

Power plants in Tennessee · Transmission lines in Tennessee

Other requests in Carroll County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem