United States › Grid › Interconnection queues › Georgia
SOLAR · SOUTHEASTSolar project IC-1055, Coffee County
Solar project IC-1055, Coffee County is a 200 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Coffee County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Aug 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-1055
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Douglas - Kettle Creek Primary 230 kV Line
- Location
- Coffee County, Georgia
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 26 August 2022
- Proposed online date
- October 2027
Location
Marker shows the centre of Coffee County; the queue data does not give exact sites.
Other requests in Coffee County
- Solar project IC-539, Coffee CountySolar · 250 MW · withdrawn
- Solar + storage project IC-963, Coffee CountySolar + storage · 200 MW · withdrawn
- Solar project IC-550, Coffee CountySolar · 143 MW · withdrawn
- Solar project IC-557, Coffee CountySolar · 70.4 MW · withdrawn
- Solar project IC-904, Coffee CountySolar · 64.0 MW · withdrawn
- Solar project IC-554, Coffee CountySolar · 57.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem