Solar project IC-1055, Coffee County

Solar project IC-1055, Coffee County is a 200 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Coffee County, Georgia, connecting to Southern Company.

Queue statusConsented
  1. PlanningQueued Aug 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IC-1055
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Douglas - Kettle Creek Primary 230 kV Line
Location
Coffee County, Georgia
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Active
Entered queue
26 August 2022
Proposed online date
October 2027

Location

Marker shows the centre of Coffee County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Coffee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem