SOLAR + STORAGE Β· SOUTHEASTSolar + storage project IC-963, Coffee County
Solar + storage project IC-963, Coffee County is a 200 MW solar + storage request withdrawn in the Southeast interconnection queue, in Coffee County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2021 (completed)
- Withdrawn / abandonedOct 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-963
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Denton Still Rd - Douglas 230 kV Line
- Location
- Coffee County, Georgia
- Technology
- Solar: 200 MW Β· Battery
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 9 June 2021
- Withdrawn
- October 2021
Location
Marker shows the centre of Coffee County; the queue data does not give exact sites.
Other requests in Coffee County
- Solar project IC-1055, Coffee CountySolar Β· 200 MW Β· agreement signed
- Solar project IC-539, Coffee CountySolar Β· 250 MW Β· withdrawn
- Solar project IC-550, Coffee CountySolar Β· 143 MW Β· withdrawn
- Solar project IC-557, Coffee CountySolar Β· 70.4 MW Β· withdrawn
- Solar project IC-904, Coffee CountySolar Β· 64.0 MW Β· withdrawn
- Solar project IC-554, Coffee CountySolar Β· 57.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem