Withdrawn queue requests in Missouri, Southeast

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown449,276 MW
Active in queue5,999 MW27 requests
Agreement signed3,459 MW15 requests
Withdrawn449,276 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

44 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-113, Randolph County
Onshore wind
500 MWWithdrawn / abandoned Randolph, MOSoutheast Jan 2023target 2026
Onshore wind project GI-114, Randolph County
Onshore wind
500 MWWithdrawn / abandoned Randolph, MOSoutheast Jan 2023target 2026
Gas project GI-99, Butler County
Gas
470 MWWithdrawn / abandoned Butler, MOSoutheast Jul 2022target 2026
Solar project GI-85, Dade County
Solar
436 MWWithdrawn / abandoned Dade, MOSoutheast Sep 2019target 2027
Solar project GI-97, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Jan 2022target 2024
Solar project GI-106, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2022target 2024
Solar project GI-74, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Solar project GI-72, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Nov 2018target 2021
Solar project GI-76, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Solar project GI-73, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Onshore wind project GI-50, Atchison County
Onshore wind
300 MWWithdrawn / abandoned Atchison, MOSoutheast Dec 2014target 2016
Solar project GI-75, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Solar project GI-70, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Solar project GI-71, New Madrid County
Solar
250 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Solar project GI-98, New Madrid County
Solar
250 MWWithdrawn / abandoned New Madrid, MOSoutheast Jan 2022target 2024
Onshore wind project GI-79, Knox County
Onshore wind
250 MWWithdrawn / abandoned Knox, MOSoutheast Jan 2019target 2021
Solar project GI-80, Callaway County
Solar
250 MWWithdrawn / abandoned Callaway, MOSoutheast Jan 2019target 2021
Solar project GI-107, New Madrid County
Solar
250 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2022target 2024
Onshore wind project GI-67, Nodaway County
Onshore wind
250 MWWithdrawn / abandoned Nodaway, MOSoutheast Mar 2018target 2020
Solar project GI-94, Jasper County
Solar
225 MWWithdrawn / abandoned Jasper, MOSoutheast Dec 2020target 2023
Solar project GI-62, New Madrid County
Solar
202 MWWithdrawn / abandoned New Madrid, MOSoutheast Oct 2017target 2020
Onshore wind project GI-37, Clinton County
Onshore wind
201 MWWithdrawn / abandoned Clinton, MOSoutheast Jun 2009target 2010
Onshore wind project GI-51, Dekalb County
Onshore wind
200 MWWithdrawn / abandoned Dekalb, MOSoutheast Mar 2015target 2016
Solar project GI-124, Vernon County
Solar
200 MWWithdrawn / abandoned Vernon, MOSoutheast Dec 2024target 2028
Solar project GI-68, Jasper County
Solar
200 MWWithdrawn / abandoned Jasper, MOSoutheast May 2018target 2023
Solar project GI-84, New Madrid County
Solar
196 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2019target 2021
Onshore wind project GI-92, Howard County
Onshore wind
170 MWWithdrawn / abandoned Howard, MOSoutheast Sep 2020target 2023
Solar project GI-119, St Clair County
Solar
166 MWWithdrawn / abandoned St Clair, MOSoutheast Aug 2023target 2027
Solar project GI-87, Randolph County
Solar
160 MWWithdrawn / abandoned Randolph, MOSoutheast Oct 2019target 2023
Onshore wind project GI-111, Douglas County
Onshore wind
150 MWWithdrawn / abandoned Douglas, MOSoutheast Nov 2022target 2026
Onshore wind project GI-36, Nodaway County
Onshore wind
100 MWWithdrawn / abandoned Nodaway, MOSoutheast Apr 2009target 2011
Onshore wind project GI-44, Nodaway County
Onshore wind
100 MWWithdrawn / abandoned Nodaway, MOSoutheast Jan 2011target 2012
Onshore wind project GI-46, Sullivan County
Onshore wind
88.8 MWWithdrawn / abandoned Sullivan, MOSoutheast Mar 2011target 2013
Solar project GI-88, Polk County
Solar
86.5 MWWithdrawn / abandoned Polk, MOSoutheast Dec 2019target 2025
Onshore wind project GI-54, Nodaway County
Onshore wind
84.0 MWWithdrawn / abandoned Nodaway, MOSoutheast May 2016target 2018
Solar project GI-89, Scott County
Solar
80.0 MWWithdrawn / abandoned Scott, MOSoutheast Jan 2020target 2022
Onshore wind project GI-45, Jasper County
Onshore wind
80.0 MWWithdrawn / abandoned Jasper, MOSoutheast Feb 2011target 2014
Onshore wind project GI-64, Sullivan County
Onshore wind
77.5 MWWithdrawn / abandoned Sullivan, MOSoutheast Feb 2018target 2020
Onshore wind project GI-49, Sullivan County
Onshore wind
77.5 MWWithdrawn / abandoned Sullivan, MOSoutheast Jun 2013target 2014
Onshore wind project GI-56, Sullivan County
Onshore wind
77.5 MWWithdrawn / abandoned Sullivan, MOSoutheast May 2016target 2018
Gas project GI-81, Dunklin County
Gas
41.0 MWWithdrawn / abandoned Dunklin, MOSoutheast Mar 2019target 2019
Gas project GI-100, Butler County
Gas
40.0 MWWithdrawn / abandoned Butler, MOSoutheast Jul 2022target 2026
Solar project GI-115, Caldwell County
Solar
35.0 MWWithdrawn / abandoned Caldwell, MOSoutheast Feb 2023target 2025
Solar project GI-118, Mississippi County
Solar
32.0 MWWithdrawn / abandoned Mississippi, MOSoutheast Jul 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)