United States βΊ Grid βΊ Interconnection queues βΊ Missouri
ONSHORE WIND Β· SOUTHEASTOnshore wind project GI-111, Douglas County
Onshore wind project GI-111, Douglas County is a 150 MW onshore wind request withdrawn in the Southeast interconnection queue, in Douglas County, Missouri, connecting to Associated Electric Cooperative, Incorporated.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-111
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Associated Electric Cooperative, Incorporated
- Connection point (POI)
- Mansfield-Gainesville 161 kV line
- Location
- Douglas County, Missouri
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 22 November 2022
- Proposed online date
- December 2026
Location
Marker shows the centre of Douglas County; the queue data does not give exact sites.
Other requests in Douglas County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem