SOLAR Β· SOUTHEAST

Solar project GI-84, New Madrid County

Solar project GI-84, New Madrid County is a 196 MW solar request withdrawn in the Southeast interconnection queue, in New Madrid County, Missouri, connecting to Associated Electric Cooperative, Incorporated.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-84
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Associated Electric Cooperative, Incorporated
Connection point (POI)
New Madrid 345 kV
Location
New Madrid County, Missouri
Technology
Solar: 196 MW
Total requested
196 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
22 August 2019
Proposed online date
December 2021

Location

Marker shows the centre of New Madrid County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in New Madrid County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem