United States βΊ Grid βΊ Interconnection queues βΊ Missouri
SOLAR Β· SOUTHEASTSolar project GI-88, Polk County
Solar project GI-88, Polk County is a 86.5 MW solar request withdrawn in the Southeast interconnection queue, in Polk County, Missouri, connecting to Associated Electric Cooperative, Incorporated.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2019 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-88
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Associated Electric Cooperative, Incorporated
- Connection point (POI)
- Eudora 69 kV
- Location
- Polk County, Missouri
- Technology
- Solar: 86.5 MW
- Total requested
- 86.5 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 20 December 2019
- Proposed online date
- August 2025
Location
Marker shows the centre of Polk County; the queue data does not give exact sites.
Other requests in Polk County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem