United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in SPP (Southwest Power Pool) (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8215.1 GW
Active in queue15.1 GW82 requests
Agreement signed1,004 MW9 requests
Withdrawn33671.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

82 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2023-204, Morris County
Gas
915 MWIn study Morris, TXSPP Oct 2023target 2028
Gas project GEN-2023-222, Gage County
Gas
478 MWIn study Gage, NESPP Oct 2023target 2030
Gas project GEN-2023-224, Lancaster County
Gas
478 MWIn study Lancaster, NESPP Oct 2023target 2029
Solar + storage project GEN-2023-102, Woods County
Solar + storage
475 MWIn study Woods, OKSPP Oct 2023target 2029
Onshore wind project GEN-2022-161, Butler County
Onshore wind
360 MWIn study Butler, KSSPP Feb 2023target 2029
Solar project GEN-2023-015, Finney County
Solar
330 MWIn study Finney, KSSPP Oct 2023target 2026
Battery storage project GEN-2022-139, Harrison County
Battery storage
300 MWIn study Harrison, TXSPP Feb 2023target 2030
Solar project GEN-2023-099, Jackson County
Solar
300 MWIn study Jackson, KSSPP Oct 2023target 2030
Onshore wind project GEN-2023-107, Finney County
Onshore wind
300 MWIn study Finney, KSSPP Oct 2023target 2030
Gas project GEN-2023-079, Cass County
Gas
273 MWIn study Cass, NESPP Oct 2023target 2032
Gas project GEN-2023-077, Cass County
Gas
255 MWIn study Cass, NESPP Oct 2023target 2028
Gas project GEN-2023-078, Cass County
Gas
255 MWIn study Cass, NESPP Oct 2023target 2028
Solar project GEN-2023-220, Osage County
Solar
250 MWIn study Osage, KSSPP Oct 2023target 2029
Solar project GEN-2023-221, Osage County
Solar
250 MWIn study Osage, KSSPP Oct 2023target 2029
Solar + storage project GEN-2023-199, Dakota County
Solar + storage
250 MWIn study Dakota, NESPP Oct 2023target 2027
Gas project GEN-2023-223, Gage County
Gas
239 MWIn study Gage, NESPP Oct 2023target 2030
Solar project GEN-2022-214, Sumner County
Solar
239 MWIn study Sumner, KSSPP Mar 2023target 2028
Onshore wind project GEN-2023-229, Caddo County
Onshore wind
230 MWIn study Caddo, OKSPP Oct 2023target 2029
Gas project GEN-2023-225, Lancaster County
Gas
217 MWIn study Lancaster, NESPP Oct 2023target 2029
Onshore wind project GEN-2022-176, Nowata County
Onshore wind
215 MWIn study Nowata, OKSPP Feb 2023target 2028
Gas project GEN-2022-147, Hale County
Gas
203 MWIn study Hale, TXSPP Feb 20232025
Battery storage project GEN-2023-037, Wyandotte County
Battery storage
200 MWIn study Wyandotte, KSSPP Oct 2023target 2028
Battery storage project GEN-2022-155, Oklahoma County
Battery storage
200 MWIn study Oklahoma, OKSPP Feb 2023target 2027
Solar project GEN-2023-038, Coal County
Solar
200 MWIn study Coal, OKSPP Oct 2023target 2026
Solar + storage project GEN-2023-064, Le Flore County
Solar + storage
200 MWIn study Le Flore, OKSPP Oct 2023target 2029
Battery storage project GEN-2022-142, Clay County
Battery storage
200 MWIn study Clay, MOSPP Feb 2023target 2030
Other project GEN-2023-059, Harrison County
Other
200 MWIn study Harrison, TXSPP Sep 2023target 2029
Battery storage project GEN-2022-144, Jackson County
Battery storage
200 MWIn study Jackson, MOSPP Feb 2023target 2030
Solar project GEN-2023-035, Grady County
Solar
200 MWIn study Grady, OKSPP Oct 2023target 2026
Battery storage project GEN-2022-130, Sebastian County
Battery storage
200 MWIn study Sebastian, ARSPP Feb 2023target 2030
Battery storage project GEN-2023-SR8, Hansford County
Battery storage
200 MWAgreement signed Hansford, TXSPP Feb 2023target 2026
Battery storage project GEN-2022-143, Marshall County
Battery storage
200 MWIn study Marshall, OKSPP Feb 2023target 2030
Battery storage project GEN-2023-033, Clay County
Battery storage
200 MWIn study Clay, MOSPP Oct 2023target 2028
Solar project GEN-2023-177, Garvin County
Solar
200 MWIn study Garvin, OKSPP Oct 2023target 2028
Onshore wind project GEN-2023-172, Kearny County
Onshore wind
200 MWIn study Kearny, KSSPP Oct 2023target 2029
Solar project GEN-2023-210, Lincoln County
Solar
191 MWIn study Lincoln, OKSPP Oct 2023target 2026
Solar project GEN-2023-205, Hughes County
Solar
180 MWIn study Hughes, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-136, Bryan County
Battery storage
180 MWIn study Bryan, OKSPP Feb 2023target 2030
Battery storage project GEN-2022-145, Johnston County
Battery storage
180 MWIn study Johnston, OKSPP Feb 2023target 2030
Solar + storage project GEN-2023-193, Harrison County
Solar + storage
175 MWIn study Harrison, TXSPP Oct 2023target 2028
Solar + storage project GEN-2022-111, Marion County
Solar + storage
150 MWIn study Marion, TXSPP Feb 2023target 2027
Battery storage project GEN-2022-235, Canadian County
Battery storage
150 MWIn study Canadian, OKSPP Feb 2023target 2028
Solar project GEN-2023-GR5, Lamb County
Solar
150 MWAgreement signed Lamb, TXSPP Jul 2023target 2026
Battery storage project GEN-2023-170, Chariton County
Battery storage
150 MWIn study Chariton, MOSPP Oct 2023target 2028
Solar project GEN-2023-SR28, Ford County
Solar
150 MWAgreement signed Ford, KSSPP Oct 20232025
Battery storage project GEN-2023-057, Pawnee County
Battery storage
150 MWIn study Pawnee, OKSPP Oct 2023target 2028
Battery storage project GEN-2023-171, Jackson County
Battery storage
150 MWIn study Jackson, MOSPP Oct 2023target 2028
Battery storage project GEN-2022-238, Pottawatomie County
Battery storage
150 MWIn study Pottawatomie, OKSPP Feb 2023target 2028
Solar + storage project GEN-2023-230, Bossier Parish County
Solar + storage
150 MWIn study Bossier Parish, LASPP Oct 2023target 2028
Solar project GEN-2023-132, Craighead County
Solar
150 MWIn study Craighead, ARSPP Oct 2023target 2028
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)