GAS · SPPGas project GEN-2023-077, Cass County
Gas project GEN-2023-077, Cass County is a 255 MW gas request in interconnection study in the SPP interconnection queue, in Cass County, Nebraska, connecting to OPPD.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2023-077
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Substation 3740 345 kV
- Location
- Cass County, Nebraska
- Technology
- Gas: 255 MW
- Total requested
- 255 MW
- Service type
- Energy only (ERIS)
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 2 October 2023
- Proposed online date
- February 2028
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
- Gas project GEN-2020-038, Cass CountyGas · 273 MW · agreement signed
- Gas project GEN-2024-213, Cass CountyGas · 360 MW · in study
- Gas project GEN-2024-211, Cass CountyGas · 303 MW · in study
- Gas project GEN-2024-212, Cass CountyGas · 303 MW · in study
- Gas project GEN-2023-079, Cass CountyGas · 273 MW · in study
- Gas project GEN-2023-078, Cass CountyGas · 255 MW · in study
- Other project GEN-2025-SR26, Cass CountyOther · 200 MW · in study
- Battery storage project GEN-2021-040, Cass CountyBattery storage · 200 MW · in study
- Solar project GEN-2021-108, Cass CountySolar · 182 MW · in study
- Battery storage project GEN-2018-033, Cass CountyBattery storage · 200 MW · suspended
- Gas project GEN-2020-035, Cass CountyGas · 425 MW · withdrawn
- Solar + storage project GEN-2020-036, Cass CountySolar + storage · 303 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem