United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
GAS Β· SPPGas project GEN-2020-035, Cass County
Gas project GEN-2020-035, Cass County is a 425 MW gas request withdrawn in the SPP interconnection queue, in Cass County, Nebraska, connecting to OPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedSep 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingMay 2023 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2020-035
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Substation 3740; 345kV
- Location
- Cass County, Nebraska
- Technology
- Gas: 425 MW
- Total requested
- 425 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 April 2020
- Proposed online date
- May 2023
- Came online
- May 2023
- Withdrawn
- September 2022
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
- Gas project GEN-2020-038, Cass CountyGas Β· 273 MW Β· agreement signed
- Gas project GEN-2024-213, Cass CountyGas Β· 360 MW Β· in study
- Gas project GEN-2024-211, Cass CountyGas Β· 303 MW Β· in study
- Gas project GEN-2024-212, Cass CountyGas Β· 303 MW Β· in study
- Gas project GEN-2023-079, Cass CountyGas Β· 273 MW Β· in study
- Gas project GEN-2023-077, Cass CountyGas Β· 255 MW Β· in study
- Gas project GEN-2023-078, Cass CountyGas Β· 255 MW Β· in study
- Other project GEN-2025-SR26, Cass CountyOther Β· 200 MW Β· in study
- Battery storage project GEN-2021-040, Cass CountyBattery storage Β· 200 MW Β· in study
- Solar project GEN-2021-108, Cass CountySolar Β· 182 MW Β· in study
- Battery storage project GEN-2018-033, Cass CountyBattery storage Β· 200 MW Β· suspended
- Solar + storage project GEN-2020-036, Cass CountySolar + storage Β· 303 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem