United States › Grid › Interconnection queues › Oklahoma
SOLAR · SPPSolar project GEN-2023-038, Coal County
Solar project GEN-2023-038, Coal County is a 200 MW solar request in interconnection study in the SPP interconnection queue, in Coal County, Oklahoma, connecting to OGE.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2023-038
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Lula 138 kV Substation
- Location
- Coal County, Oklahoma
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 2 October 2023
- Proposed online date
- September 2026
Location
Marker shows the centre of Coal County; the queue data does not give exact sites.
Other requests in Coal County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem