Battery storage project GEN-2022-110, Coal County

Battery storage project GEN-2022-110, Coal County is a 150 MW battery storage request withdrawn in the SPP interconnection queue, in Coal County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-110
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Lehigh 138kV Station
Location
Coal County, Oklahoma
Technology
Battery: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
10 February 2023
Proposed online date
April 2026
Withdrawn
March 2025

Location

Marker shows the centre of Coal County; the queue data does not give exact sites.