United States › Grid › Interconnection queues › Oklahoma
SOLAR + STORAGE · SPPSolar + storage project GEN-2023-064, Le Flore County
Solar + storage project GEN-2023-064, Le Flore County is a 200 MW solar + storage request in interconnection study in the SPP interconnection queue, in Le Flore County, Oklahoma, connecting to SWPA.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2023-064
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SWPA
- Connection point (POI)
- RS Kerr-Stigler 161 kV line
- Location
- Le Flore County, Oklahoma
- Technology
- Solar: 200 MW · Battery
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 2 October 2023
- Proposed online date
- December 2029
Location
Marker shows the centre of Le Flore County; the queue data does not give exact sites.
Other requests in Le Flore County
- Gas project GEN-2024-286, Le Flore CountyGas · 136 MW · in study
- Onshore wind project GEN-2016-028, Le Flore CountyOnshore wind · 100 MW · built
- Coal project GEN-2008-030, Le Flore CountyCoal · 660 MW · withdrawn
- Coal project GEN-2006-042, Le Flore CountyCoal · 600 MW · withdrawn
- Solar project GEN-2021-SR4, Le Flore CountySolar · 22.2 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem