πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Texas, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6116.6 GW
Active in queue20.6 GW79 requests
Agreement signed4,003 MW18 requests
Withdrawn31170.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

61 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-377, Harrison County
Gas
1,350 MWIn study Harrison, TXSPP Mar 2025target 2031
Gas project GEN-2023-204, Morris County
Gas
915 MWIn study Morris, TXSPP Oct 2023target 2028
Solar + storage project GEN-2024-266, Potter County
Solar + storage
500 MWIn study Potter, TXSPP Mar 2025target 2033
Onshore wind project ERAS-2025-021, Hale County
Onshore wind
500 MWIn study Hale, TXSPP Oct 2025target 2030
Gas project GEN-2024-343, Harrison County
Gas
471 MWIn study Harrison, TXSPP Mar 2025target 2030
Onshore wind project GEN-2024-109, Bailey County
Onshore wind
401 MWIn study Bailey, TXSPP Mar 2025target 2031
Solar + storage project GEN-2021-090, Yoakum County
Solar + storage
400 MWIn study Yoakum, TXSPP Apr 2021target 2028
Solar project ERAS-2025-028, Hockley County
Solar
384 MWIn study Hockley, TXSPP Oct 2025target 2030
Onshore wind project GEN-2020-067, Terry County
Onshore wind
353 MWIn study Terry, TXSPP Apr 2020target 2026
Solar + storage project GEN-2024-280, Andrews County
Solar + storage
350 MWIn study Andrews, TXSPP Mar 2025target 2029
Solar project GEN-2024-046, Hansford County
Solar
345 MWIn study Hansford, TXSPP Oct 2024target 2029
Solar project GEN-2024-045, Hansford County
Solar
345 MWIn study Hansford, TXSPP Oct 2024target 2029
Solar project GEN-2024-025, Bowie County
Solar
300 MWIn study Bowie, TXSPP Oct 2024target 2030
Solar project GEN-2024-078, Hutchinson County
Solar
300 MWIn study Hutchinson, TXSPP Oct 2024target 2029
Solar project GEN-2024-099, Castro County
Solar
300 MWIn study Castro, TXSPP Mar 2025target 2031
Battery storage project GEN-2022-139, Harrison County
Battery storage
300 MWIn study Harrison, TXSPP Feb 2023target 2030
Battery storage project GEN-2024-230, Wilbarger County
Battery storage
300 MWIn study Wilbarger, TXSPP Mar 2025target 2030
Solar + storage project GEN-2024-050, Castro County
Solar + storage
300 MWIn study Castro, TXSPP Oct 2024target 2028
Solar + storage project GEN-2024-336, Yoakum County
Solar + storage
300 MWIn study Yoakum, TXSPP Mar 2025target 2029
Battery storage project GEN-2024-SR15, Yoakum County
Battery storage
300 MWIn study Yoakum, TXSPP Oct 2024target 2026
Solar + storage project GEN-2024-364, Randall County
Solar + storage
300 MWIn study Randall, TXSPP Mar 2025target 2028
Solar project GEN-2024-317, Cottle County
Solar
300 MWIn study Cottle, TXSPP Mar 2025target 2030
Solar project GEN-2024-077, Hutchinson County
Solar
300 MWIn study Hutchinson, TXSPP Oct 2024target 2029
Solar project GEN-2024-068, Morris County
Solar
300 MWIn study Morris, TXSPP Oct 2024target 2028
Onshore wind project GEN-2025-GR6, Dimmit County
Onshore wind
300 MWIn study Dimmit, TXSPP Nov 2025
Solar + storage project GEN-2024-015, Yoakum County
Solar + storage
280 MWIn study Yoakum, TXSPP Oct 2024target 2028
Solar project GEN-2024-063, Lamb County
Solar
256 MWIn study Lamb, TXSPP Oct 2024target 2027
Solar project GEN-2024-232, Houston County
Solar
250 MWIn study Houston, TXSPP Mar 2025target 2029
Onshore wind project GEN-2024-042, Floyd County
Onshore wind
250 MWIn study Floyd, TXSPP Oct 2024target 2028
Solar project GEN-2024-153, Randall County
Solar
250 MWIn study Randall, TXSPP Mar 2025target 2029
Onshore wind project GEN-2024-041, Floyd County
Onshore wind
250 MWIn study Floyd, TXSPP Oct 2024target 2029
Battery storage project GEN-2024-368, Gray County
Battery storage
250 MWIn study Gray, TXSPP Mar 2025target 2028
Onshore wind project GEN-2024-145, Dallam County
Onshore wind
250 MWIn study Dallam, TXSPP Mar 2025target 2032
Onshore wind project GEN-2024-143, Dallam County
Onshore wind
250 MWIn study Dallam, TXSPP Mar 2025target 2032
Battery storage project ERAS-2025-027, Yoakum County
Battery storage
250 MWIn study Yoakum, TXSPP Oct 2025target 2028
Gas project ERAS-2025-016, Lamb County
Gas
233 MWIn study Lamb, TXSPP Oct 2025target 2029
Gas project ERAS-2025-002, Hale County
Gas
217 MWIn study Hale, TXSPP Sep 2025target 2027
Gas project GEN-2022-147, Hale County
Gas
203 MWIn study Hale, TXSPP Feb 20232025
Solar project GEN-2024-229, Wilbarger County
Solar
200 MWIn study Wilbarger, TXSPP Mar 2025target 2030
Other project GEN-2023-059, Harrison County
Other
200 MWIn study Harrison, TXSPP Sep 2023target 2029
Battery storage project GEN-2020-060, Lubbock County
Battery storage
200 MWIn study Lubbock, TXSPP Apr 2020target 2027
Battery storage project GEN-2021-038, Titus County
Battery storage
200 MWIn study Titus, TXSPP Apr 2021target 2028
Battery storage project GEN-2024-355, Lubbock County
Battery storage
199 MWIn study Lubbock, TXSPP Mar 2025target 2030
Battery storage project GEN-2024-178, Harrison County
Battery storage
199 MWIn study Harrison, TXSPP Mar 2025target 2029
Solar project GEN-2022-038, Harrison County
Solar
180 MWIn study Harrison, TXSPP Jun 2022target 2029
Battery storage project GEN-2019-065, Smith County
Battery storage
180 MWIn study Smith, TXSPP May 2019target 2026
Solar + storage project GEN-2023-193, Harrison County
Solar + storage
175 MWIn study Harrison, TXSPP Oct 2023target 2028
Solar + storage project GEN-2024-122, Marion County
Solar + storage
160 MWIn study Marion, TXSPP Mar 2025target 2029
Solar + storage project GEN-2022-111, Marion County
Solar + storage
150 MWIn study Marion, TXSPP Feb 2023target 2027
Solar project GEN-2024-376, Sabine County
Solar
142 MWIn study Sabine, TXSPP Mar 2025target 2028
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)