Interconnection queue in Kansas, SPP (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4813.5 GW
Active in queue13.5 GW48 requests
Agreement signed0.0 MW0 requests
Withdrawn184,089 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

48 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-129, Labette County
Gas
910 MWIn study Labette, KSSPP Mar 2025target 2030
Gas project GEN-2024-249, Pottawatomie County
Gas
721 MWIn study Pottawatomie, KSSPP Mar 2025target 2032
Gas project ERAS-2025-008, Sumner County
Gas
721 MWIn study Sumner, KSSPP Sep 2025target 2029
Gas project ERAS-2025-006, Reno County
Gas
718 MWIn study Reno, KSSPP Sep 2025target 2030
Gas project ERAS-2025-017, Finney County
Gas
600 MWIn study Finney, KSSPP Sep 2025target 2029
Onshore wind project GEN-2024-102, Finney County
Onshore wind
401 MWIn study Finney, KSSPP Mar 2025target 2031
Solar project GEN-2024-125, Elk County
Solar
400 MWIn study Elk, KSSPP Mar 2025target 2028
Solar project GEN-2024-136, Scott County
Solar
400 MWIn study Scott, KSSPP Mar 2025target 2029
Solar + storage project ERAS-2025-015, Finney County
Solar + storage
400 MWIn study Finney, KSSPP Sep 2025target 2029
Onshore wind project GEN-2024-258, Allen County
Onshore wind
300 MWIn study Allen, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-137, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Solar + storage project GEN-2024-215, Cloud County
Solar + storage
300 MWIn study Cloud, KSSPP Mar 2025target 2029
Onshore wind project GEN-2024-138, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-142, Mcpherson County
Onshore wind
300 MWIn study Mcpherson, KSSPP Mar 2025target 2031
Gas project GEN-2024-253, Leavenworth County
Gas
300 MWIn study Leavenworth, KSSPP Mar 2025target 2027
Battery storage project GEN-2024-339, Leavenworth County
Battery storage
300 MWIn study Leavenworth, KSSPP Mar 2025target 2029
Battery storage project GEN-2025-SR16, Sumner County
Battery storage
300 MWIn study Sumner, KSSPP Jun 2025target 2026
Onshore wind project GEN-2024-144, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Solar + storage project GEN-2024-166, Sedgwick County
Solar + storage
275 MWIn study Sedgwick, KSSPP Mar 2025target 2030
Solar project GEN-2024-139, Coffey County
Solar
250 MWIn study Coffey, KSSPP Mar 2025target 2033
Battery storage project GEN-2024-176, Reno County
Battery storage
250 MWIn study Reno, KSSPP Mar 2025target 2028
Onshore wind project GEN-2024-193, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Onshore wind project GEN-2024-194, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-330, Butler County
Battery storage
225 MWIn study Butler, KSSPP Mar 2025target 2028
Solar project GEN-2024-257, Pratt County
Solar
220 MWIn study Pratt, KSSPP Mar 2025target 2029
Solar project GEN-2024-228, Rice County
Solar
200 MWIn study Rice, KSSPP Mar 2025target 2030
Solar project GEN-2024-287, Crawford County
Solar
200 MWIn study Crawford, KSSPP Mar 2025target 2030
Solar project GEN-2024-209, Clay County
Solar
199 MWIn study Clay, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-189, Ford County
Battery storage
199 MWIn study Ford, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-320, Wyandotte County
Battery storage
199 MWIn study Wyandotte, KSSPP Mar 2025target 2028
Solar + storage project GEN-2024-272, Pratt County
Solar + storage
199 MWIn study Pratt, KSSPP Mar 2025target 2029
Solar + storage project GEN-2024-218, Seward County
Solar + storage
199 MWIn study Seward, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-319, Wyandotte County
Battery storage
199 MWIn study Wyandotte, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-121, Leavenworth County
Battery storage
199 MWIn study Leavenworth, KSSPP Mar 2025target 2028
Solar project GEN-2024-274, Harper County
Solar
175 MWIn study Harper, KSSPP Mar 2025target 2030
Battery storage project ERAS-2025-029, Wyandotte County
Battery storage
170 MWIn study Wyandotte, KSSPP Oct 2025target 2027
Solar + storage project GEN-2024-205, Stafford County
Solar + storage
155 MWIn study Stafford, KSSPP Mar 2025target 2029
Battery storage project GEN-2024-276, Shawnee County
Battery storage
150 MWIn study Shawnee, KSSPP Mar 2025target 2030
Solar project GEN-2024-210, Cheyenne County
Solar
150 MWIn study Cheyenne, KSSPP Mar 2025target 2028
Solar + storage project ERAS-2025-032, Stafford County
Solar + storage
150 MWIn study Stafford, KSSPP Oct 2025target 2029
Solar + storage project ERAS-2025-033, Ford County
Solar + storage
150 MWIn study Ford, KSSPP Oct 2025target 2027
Battery storage project GEN-2025-SR4, Edwards County
Battery storage
150 MWIn study Edwards, KSSPP Aug 2025target 2028
Other project ERAS-2025-031, Wyandotte County
Other
150 MWIn study Wyandotte, KSSPP Oct 2025target 2028
Battery storage project GEN-2025-SR3, Clark County
Battery storage
150 MWIn study Clark, KSSPP Aug 2025target 2028
Battery storage project GEN-2024-277, Shawnee County
Battery storage
150 MWIn study Shawnee, KSSPP Mar 2025target 2030
Solar project GEN-2024-288, Cloud County
Solar
130 MWIn study Cloud, KSSPP Mar 2025target 2030
Solar project ERAS-2025-019, Edwards County
Solar
80.0 MWIn study Edwards, KSSPP Oct 2025target 2028
Battery storage project GEN-2024-322, Graham County
Battery storage
75.0 MWIn study Graham, KSSPP Mar 2025target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)