United States › Grid › Interconnection queues › Kansas
SOLAR · SPPSolar project ERAS-2025-019, Edwards County
Solar project ERAS-2025-019, Edwards County is a 80.0 MW solar request in interconnection study in the SPP interconnection queue, in Edwards County, Kansas, connecting to MIDW.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- ERAS-2025-019
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- MIDW
- Connection point (POI)
- 5th Street Substation
- Location
- Edwards County, Kansas
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- NRIS and ERIS
- Study phase
- ERAS
- Queue status
- Active
- Entered queue
- 2 October 2025
- Proposed online date
- December 2028
Location
Marker shows the centre of Edwards County; the queue data does not give exact sites.
Other requests in Edwards County
- Solar project GEN-2019-055, Edwards CountySolar · 150 MW · agreement signed
- Battery storage project GEN-2019-053, Edwards CountyBattery storage · 50.0 MW · agreement signed
- Battery storage project GEN-2025-SR4, Edwards CountyBattery storage · 150 MW · in study
- Solar project GEN-2022-065, Edwards CountySolar · 145 MW · in study
- Onshore wind project GEN-2004-014, Edwards CountyOnshore wind · 152 MW · built
- Onshore wind project GEN-2008-060, Edwards CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2024-196, Edwards CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-205, Edwards CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-204, Edwards CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2024-195, Edwards CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2022-206, Edwards CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2024-197, Edwards CountyOnshore wind · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem