United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Solar interconnection queue in PJM (Mid-Atlantic, Midwest)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown73059.8 GW
Active in queue59.8 GW730 requests
Agreement signed21.7 GW239 requests
Withdrawn2,565120.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

730 requests ยท page 1 of 15
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH2-351
Solar
1,000 MWIn study KYPJM Mar 2022target 2027
Solar project AH2-353
Solar
1,000 MWIn study KYPJM Mar 2022target 2028
Blackwater Solar
Solar
800 MWAgreement signed Sussex, VAPJM Sep 2018target 2029
Solar project AH2-348, Daviess County
Solar
700 MWIn study Daviess, INPJM Mar 2022target 2025
Randolph Solar
Solar ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
500 MWAgreement signed Halifax, VAPJM Dec 2019target 2032
Dolphin Solar
Solar ยท Dolphin Solar LLC
450 MWIn study Fountain, INPJM Sep 2020target 2024
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Solar project AH2-352
Solar
400 MWIn study INPJM Mar 2022target 2026
Solar project AH2-257, Vermillion County
Solar
400 MWIn study Vermillion, INPJM Mar 2022target 2024
Solar project AG2-570, Brunswick County
Solar ยท Zeus Energy, LLC
400 MWIn study Brunswick, VAPJM Mar 2025target 2024
Solar project AH2-340, Stark County
Solar
350 MWIn study Stark, ILPJM Mar 2022target 2027
Solar project AG2-436, Sussex County
Solar ยท Monarch Solar, LLC
350 MWIn study Sussex, VAPJM Apr 2025target 2023
Chickahominy Solar 1 and 2
Solar
320 MWAgreement signed Charles City, VAPJM Oct 20162021
Honeybee Solar, LLC
Solar ยท Honeybee Solar Energy, LLC
301 MWIn study Brunswick, VAPJM Jan 2025target 2025
Pleasant Grove Solar
Solar ยท Deriva Energy Solar, LLC
300 MWIn study Mchenry, ILPJM Mar 2020target 2023
Yellow Wood Solar Energy Center
Solar
300 MWAgreement signed Clinton, OHPJM Mar 2019target 2026
Butterfly Meadows
Solar ยท Butterfly Meadows Solar Project, LLC
300 MWIn study Van Wert, OHPJM Sep 2020target 2024
Solar project AI1-203, Lunenburg County
Solar
300 MWIn study Lunenburg, VAPJM Sep 2022target 2027
Mammoth South Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Steward Creek Solar
Solar ยท Steward Creek Solar, LLC
300 MWIn study Lee, ILPJM Dec 2019target 2023
Dawson Solar
Solar ยท Deriva Energy Solar, LLC
300 MWIn study Mclean, ILPJM Sep 2020target 2024
Macadamia Solar
Solar
300 MWAgreement signed Washington, NCPJM Sep 2017target 2028
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Burr Oak Solar
Solar ยท Leeward Renewable Energy Development, LLC
300 MWIn study Dekalb, ILPJM Aug 2020target 2023
South Dixon Solar
Solar ยท Deriva Energy Solar, LLC
300 MWIn study Lee, ILPJM Mar 2020target 2022
Solar project AG2-363, Tazewell County
Solar ยท Mackinaw Solar LLC
300 MWIn study Tazewell, ILPJM Mar 2025target 2024
Black Diamond Solar
Solar ยท Black Diamond Solar Power, LLC
299 MWIn study Christian, ILPJM Mar 2019target 2022
Solar project AI1-085, Wayne County
Solar
290 MWIn study Wayne, INPJM Jul 2022target 2030
Solar project AH2-322, Pittsylvania County
Solar
290 MWIn study Pittsylvania, VAPJM Mar 2022target 2025
Solar project AG2-453, Kendall County
Solar ยท Fox Valley Energy Facility, LLC
280 MWIn study Kendall, ILPJM Feb 2025target 2024
Solar project AH2-342, Stark County
Solar
280 MWIn study Stark, ILPJM Mar 2022target 2027
Solar project AI2-081, Logan County
Solar
271 MWIn study Logan, OHPJM Feb 2023target 2025
Beacon Solar
Solar ยท Beacon Solar, LLC
260 MWIn study Rock Island, ILPJM Sep 2020target 2023
Mayapple Solar
Solar
260 MWAgreement signed Pulaski, INPJM Sep 2020target 2027
Gipper Solar Farm
Solar ยท Gipper Solar Farm, LLC
255 MWIn study Whiteside, ILPJM Oct 2020target 2023
Solar project AI1-040, Elk County
Solar
250 MWIn study Elk, PAPJM Apr 2022target 2025
Goldfinch Solar
Solar ยท Goldfinch Solar, LLC
250 MWAgreement signed Mason, KYPJM Feb 2020target 2030
Solar project AH2-069, Wythe County
Solar
250 MWIn study Wythe, VAPJM Jan 2022target 2025
Solar project AG2-029, Noble County
Solar ยท Southern Pike Solar LLC
250 MWIn study Noble, INPJM Feb 2025target 2024
Solar project AG2-163, Fountain County
Solar ยท Dolphin Solar LLC
250 MWIn study Fountain, INPJM Feb 2025target 2024
Cadence Solar Energy Center
Solar
240 MWAgreement signed Union, OHPJM Mar 2018target 2026
Sycamore Cross Solar
Solar
240 MWAgreement signed Isle Of Wight, VAPJM Mar 2017target 2026
Solar project AH1-055, Jackson County
Solar ยท Furnace Solar, LLC
220 MWIn study Jackson, OHPJM Feb 2025target 2026
Eastern Cottontail Solar
Solar
220 MWAgreement signed Fairfield, OHPJM Jan 2019target 2028
Solar project AG2-245, Starke County
Solar ยท STARKE CENTRAL PROJECT, LLC
210 MWIn study Starke, INPJM Mar 2025target 2023
Solar project AG2-184, Knott County
Solar ยท STMO bn, LLC
210 MWIn study Knott, KYPJM Feb 2025target 2024
Broomstick Solar Energy Centergy Center
Solar
210 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Fountain Point Solar
Solar ยท Fountain Point Solar Energy LLC
207 MWIn study Union, OHPJM Aug 2018target 2021
Page 1 of 15

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)