United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Projects with signed interconnection agreements in PJM (Mid-Atlantic, Midwest) (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown12811.1 GW
Active in queue16.6 GW178 requests
Agreement signed11.1 GW128 requests
Withdrawn71947.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

128 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Fourth Quarter
Battery storage ยท Fourth Quarter BESS, LLC
500 MWAgreement signed Montgomery, MDPJM Oct 2020target 2030
West Lorain Power Plant 345 kV
Gas
406 MWAgreement signed Lorain, OHPJM Sep 2020target 2031
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Mammoth South Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Jade Meadow III Solar Facility
Solar + storage
300 MWAgreement signed Garrett, MDPJM Sep 2020target 2028
Mayapple Solar
Solar
260 MWAgreement signed Pulaski, INPJM Sep 2020target 2027
Goldfinch Solar
Solar ยท Goldfinch Solar, LLC
250 MWAgreement signed Mason, KYPJM Feb 2020target 2030
Woods Landing Energy Storage
Battery storage
250 MWAgreement signed Atlantic, NJPJM Mar 2020target 2030
Honey Creek Solar
Solar + storage
200 MWAgreement signed White, INPJM Feb 2020target 2027
Warren County Wind Energy Center
Onshore wind
200 MWAgreement signed INPJM Sep 2020target 2028
Moss Creek Solar
Solar
200 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Prairie Creek Wind
Onshore wind ยท Prairie Creek Wind, LLC
200 MWAgreement signed Blackford, INPJM Mar 2020target 2029
CPV Backbone Solar
Solar
175 MWAgreement signed Garrett, MDPJM Mar 2020target 2025
French Creek Solar and BESS
Solar + storage ยท French Creek Energy, LLC
150 MWAgreement signed Erie, PAPJM Sep 2020target 2029
Palomino Solar
Solar
150 MWAgreement signed Highland, OHPJM Aug 2020target 2027
Pulaski Solar
Solar
150 MWAgreement signed Pulaski, VAPJM Jan 2020target 2028
Two Rivers Storage
Battery storage
150 MWAgreement signed Hudson, NJPJM Mar 2020target 2028
Deep Lake Solar
Solar
150 MWAgreement signed Nicholas, WVPJM Mar 2020target 2029
Gemstone Solar
Solar
150 MWAgreement signed Cass, MIPJM Jan 2020target 2028
Exie Solar
Solar ยท Exie Solar, LLC
150 MWAgreement signed Green, KYPJM Sep 2020target 2028
Magley Solar Energy Center
Solar
135 MWAgreement signed Adams, INPJM Sep 2020target 2029
South Branch Solar
Solar
130 MWAgreement signed Hancock, OHPJM Mar 2020target 2026
Harvey Solar I
Solar
128 MWAgreement signed Licking, OHPJM Jun 2020target 2029
Quarter Horse Solar
Solar ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
125 MWAgreement signed Charlotte, VAPJM Sep 2020target 2031
Bluestem Solar
Solar
125 MWAgreement signed Laporte, INPJM Mar 2020target 2027
Canal Road
Solar
120 MWAgreement signed Wayne, OHPJM Mar 2020target 2027
Rainbow Trout
Solar + storage
120 MWAgreement signed Tippecanoe, INPJM Sep 2020target 2028
Union Ridge Solar
Solar
108 MWAgreement signed Licking, OHPJM Feb 2020target 2026
Summer Shade Solar
Solar + storage ยท Summer Shade Solar, LLC
106 MWAgreement signed Metcalfe, KYPJM Sep 2020target 2028
Flatrock Creek Solar II
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Swift Creek Solar
Solar + storage
100 MWAgreement signed Edgecombe, NCPJM Mar 2020target 2029
Prairie Creek Wind Phase 2
Onshore wind ยท Prairie Creek Wind Farm II, LLC
100 MWAgreement signed Blackford, INPJM Sep 2020target 2029
Flatrock Creek Solar I
Solar
100 MWAgreement signed Allen, INPJM Mar 2020target 2029
Tillman Solar Park
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Nicholas Solar
Solar
100 MWAgreement signed Nicholas, WVPJM Mar 2020target 2029
New Haven Solar
Solar
100 MWAgreement signed Mason, WVPJM Mar 2020target 2028
Remington BESS
Battery storage
100 MWAgreement signed Fauquier, VAPJM Sep 2020target 2029
Sun Chief Solar Farm
Solar
100 MWAgreement signed Jay, INPJM Jul 2020target 2027
Black Moshannon Solar
Solar + storage ยท CE-Black Moshannon OZ LLC
95.0 MWAgreement signed Centre, PAPJM Aug 2020target 2023
Red Maple Solar
Solar
94.9 MWAgreement signed Adams, ILPJM Mar 2020target 2028
Clover Creek Solar
Solar ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
90.0 MWAgreement signed Halifax, VAPJM Aug 2020target 2030
Bear Island Solar
Solar + storage
89.0 MWAgreement signed Surry, VAPJM Mar 2020target 2028
Blossom Solar
Solar
88.0 MWAgreement signed Morrow, OHPJM Mar 2020target 2027
Harvey Solar I
Solar
85.0 MWAgreement signed Licking, OHPJM Jun 2020target 2029
Prairie Flyer Energy Storage
Battery storage
85.0 MWAgreement signed Montgomery, OHPJM Sep 2020target 2028
Carnation
Solar
84.0 MWAgreement signed Fairfield, OHPJM Mar 2020target 2028
Stonecrop Solar
Solar ยท CPV Stonecrop Solar, LLC
82.0 MWAgreement signed Hardin, KYPJM Sep 2020target 2029
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)