OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15321.3 GW
Active in queue20.0 GW130 requests
Agreement signed14.3 GW90 requests
Withdrawn15321.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

153 requests Β· page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J1459, Calhoun County
Gas
670 MWWithdrawn / abandoned Calhoun, MIMISO Apr 2019target 2024
Gas project J1288, Vermillion County
Gas
667 MWWithdrawn / abandoned Vermillion, INMISO Apr 2019target 2023
Onshore wind project J1315, Cottonwood County
Onshore wind
600 MWWithdrawn / abandoned Cottonwood, MNMISO Apr 2019target 2022
Other project J1489, Ralls County
Other
500 MWWithdrawn / abandoned Ralls, MOMISO Apr 2019target 2024
Onshore wind project J1427, Benton County
Onshore wind
400 MWWithdrawn / abandoned Benton, IAMISO Apr 2019target 2022
Onshore wind project J1341, Buchanan County
Onshore wind
398 MWWithdrawn / abandoned Buchanan, IAMISO Apr 2019target 2022
Gas project J1346, Wayne County
Gas
382 MWWithdrawn / abandoned Wayne, MIMISO Apr 2019target 2022
Other project J1349, Cottonwood County
Other
335 MWWithdrawn / abandoned Cottonwood, MNMISO Apr 2019target 2023
Onshore wind project MPC04100, Grand Forks County
Onshore wind
300 MWWithdrawn / abandoned Grand Forks, NDMISO Apr 2019target 2023
Onshore wind project J1456, Sheridan County
Onshore wind
300 MWWithdrawn / abandoned Sheridan, NDMISO Apr 2019target 2023
Solar project J1413, Howard County
Solar
300 MWWithdrawn / abandoned Howard, IAMISO Apr 2019target 2022
Solar project J1337, Sherburne County
Solar
300 MWWithdrawn / abandoned Sherburne, MNMISO Apr 2019target 2022
Other project J1283, Jefferson County
Other
270 MWWithdrawn / abandoned Jefferson, ARMISO Apr 2019target 2023
Solar project J1419, Greene County
Solar
250 MWWithdrawn / abandoned Greene, INMISO Apr 2019target 2022
Solar project J1447, Porter County
Solar
250 MWWithdrawn / abandoned Porter, INMISO Apr 2019target 2025
Solar project J1412, Porter County
Solar
250 MWWithdrawn / abandoned Porter, INMISO Apr 2019target 2023
Solar project J1284, Linn County
Solar
250 MWWithdrawn / abandoned Linn, IAMISO Apr 2019target 2023
Solar project J1474, Chippewa County
Solar
200 MWWithdrawn / abandoned Chippewa, WIMISO Apr 2019target 2025
Solar project J1330, Randolph County
Solar
200 MWWithdrawn / abandoned Randolph, ILMISO Apr 2019target 2022
Solar project J1471, Lee County
Solar
200 MWWithdrawn / abandoned Lee, IAMISO Apr 2019target 2022
Solar project J1403, Ionia County
Solar
200 MWWithdrawn / abandoned Ionia, MIMISO Apr 2019target 2023
Solar project J1222, Ralls County
Solar
200 MWWithdrawn / abandoned Ralls, MOMISO Apr 2019target 2022
Solar project J1220, Rapides Parish County
Solar
200 MWWithdrawn / abandoned Rapides Parish, LAMISO Apr 2019target 2022
Solar project J1441, Terrebonne Parish County
Solar
200 MWWithdrawn / abandoned Terrebonne Parish, LAMISO Apr 2019target 2025
Onshore wind project J1366, Eau Claire County
Onshore wind
200 MWWithdrawn / abandoned Eau Claire, WIMISO Apr 2019target 2022
Solar project J1217, St. Landry Parish County
Solar
200 MWWithdrawn / abandoned St. Landry Parish, LAMISO Apr 2019target 2022
Solar project J1457, Vermillion County
Solar
200 MWWithdrawn / abandoned Vermillion, INMISO Apr 2019target 2022
Solar project J1282, Beauregard Parish County
Solar
200 MWWithdrawn / abandoned Beauregard Parish, LAMISO Apr 2019target 2022
Solar project J1332, Jasper County
Solar
200 MWWithdrawn / abandoned Jasper, INMISO Apr 2019target 2025
Solar project J1296, Gibson County
Solar
200 MWWithdrawn / abandoned Gibson, INMISO Apr 2019target 2022
Solar project J1380, Beauregard Parish County
Solar
200 MWWithdrawn / abandoned Beauregard Parish, LAMISO Apr 2019target 2023
Solar project J1469, Crittenden County
Solar
200 MWWithdrawn / abandoned Crittenden, ARMISO Apr 2019target 2022
Solar project J1322, Eaton County
Solar
200 MWWithdrawn / abandoned Eaton, MIMISO Apr 2019target 2022
Solar project J1428, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Apr 2019target 2022
Solar project J1384, Evangeline Parish County
Solar
200 MWWithdrawn / abandoned Evangeline Parish, LAMISO Apr 2019target 2022
Solar project J1395, Lyon County
Solar
200 MWWithdrawn / abandoned Lyon, MNMISO Apr 2019target 2023
Solar project J1452, Red River Parish County
Solar
200 MWWithdrawn / abandoned Red River Parish, LAMISO Apr 2019target 2022
Solar project J1204, Cumberland County
Solar
199 MWWithdrawn / abandoned Cumberland, ILMISO Apr 2019target 2025
Solar project J1237, Washtenaw County
Solar
175 MWWithdrawn / abandoned Washtenaw, MIMISO Apr 2019target 2022
Onshore wind project J1404, Sunflower County
Onshore wind
167 MWWithdrawn / abandoned Sunflower, MSMISO Apr 2019target 2022
Solar project J1260, Desha County
Solar
164 MWWithdrawn / abandoned Desha, ARMISO Apr 2019target 2021
Solar project J1356, Martin County
Solar
160 MWWithdrawn / abandoned Martin, INMISO Apr 2019target 2023
Solar project J1225, Washington County
Solar
160 MWWithdrawn / abandoned Washington, ILMISO Apr 2019target 2023
Onshore wind project J1195, Branch County
Onshore wind
150 MWWithdrawn / abandoned Branch, MIMISO Apr 2019target 2021
Solar project J1362, Muskegon County
Solar
150 MWWithdrawn / abandoned Muskegon, MIMISO Apr 2019target 2021
Solar project J1463, West Baton Rouge Parish, La County
Solar
150 MWWithdrawn / abandoned West Baton Rouge Parish, La, LAMISO Apr 2019target 2023
Solar project J1448, Caldwell County
Solar
150 MWWithdrawn / abandoned Caldwell, KYMISO Apr 2019target 2022
Battery storage project J1353, Lake County
Battery storage
150 MWWithdrawn / abandoned Lake, INMISO Apr 2019target 2023
Solar project J1394, Shiawassee County
Solar
150 MWWithdrawn / abandoned Shiawassee, MIMISO Apr 2019target 2021
Solar project J1324, Montgomery County
Solar
150 MWWithdrawn / abandoned Montgomery, ILMISO Apr 2019target 2022
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)