United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

SOLAR Β· MISO

Solar project J1332, Jasper County

Solar project J1332, Jasper County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Jasper County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1332
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
Rollin Schahfer - Lake George 345kV Line
Location
Jasper County, Indiana
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Withdrawn
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
April 2025
Withdrawn
March 2024

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Jasper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem