Onshore wind project J1195, Branch County

Onshore wind project J1195, Branch County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Branch County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedJan 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1195
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Wagner 138 kV Substation
Location
Branch County, Michigan
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
24 April 2019
Proposed online date
October 2021
Withdrawn
January 2020

Location

Marker shows the centre of Branch County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Branch County