United States βΊ Grid βΊ Interconnection queues βΊ Iowa
SOLAR Β· MISOSolar project J1471, Lee County
Solar project J1471, Lee County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Lee County, Iowa, connecting to ITC MIDWEST.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedFeb 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1471
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- ITC 161kV Wever Substation
- Location
- Lee County, Iowa
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- August 2022
- Withdrawn
- February 2022
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Other requests in Lee County
- Surplus; J1734Other Β· 120 MW Β· in study
- Solar project J1734, Lee CountySolar Β· 150 MW Β· built
- Gas project G258, Lee CountyGas Β· 50.0 MW Β· built
- Coal project G761, Lee CountyCoal Β· 28.0 MW Β· built
- Solar + storage project J3214, Lee CountySolar + storage Β· 185 MW Β· withdrawn
- Coal project G732, Lee CountyCoal Β· 34.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem