United States › Grid › Interconnection queues › Iowa

COAL · MISO

Coal project G761, Lee County

Coal project G761, Lee County is a 28.0 MW coal request built and operating in the MISO interconnection queue, in Lee County, Iowa.

Queue statusOperating
  1. PlanningQueued Mar 2007 (completed)
  2. ConsentedApr 2009 (completed)
  3. Construction (completed)
  4. OperatingDec 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G761
Grid region
MISO (Midcontinent)
Connection point (POI)
ITC Midwest Keokuk West - Keokuk Hydro 69kV
Location
Lee County, Iowa
Technology
Coal: 28.0 MW
Total requested
28.0 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
9 March 2007
Agreement signed
9 April 2009
Proposed online date
December 2014
Came online
December 2014

Location

Marker shows the centre of Lee County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Lee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem