United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J1394, Shiawassee County

Solar project J1394, Shiawassee County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Shiawassee County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedFeb 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1394
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Cornell - Layton138kV Line
Location
Shiawassee County, Michigan
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
December 2021
Withdrawn
February 2021

Location

Marker shows the centre of Shiawassee County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Shiawassee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem