United States βΊ Grid βΊ Interconnection queues βΊ Michigan
SOLAR Β· MISOSolar project J1394, Shiawassee County
Solar project J1394, Shiawassee County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Shiawassee County, Michigan, connecting to METC.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedFeb 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1394
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- Cornell - Layton138kV Line
- Location
- Shiawassee County, Michigan
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- December 2021
- Withdrawn
- February 2021
Location
Marker shows the centre of Shiawassee County; the queue data does not give exact sites.
Other requests in Shiawassee County
- Solar project J1297, Shiawassee CountySolar Β· 170 MW Β· under construction
- Onshore wind project J3865, Shiawassee CountyOnshore wind Β· 250 MW Β· in study
- Onshore wind project J3864, Shiawassee CountyOnshore wind Β· 230 MW Β· in study
- Solar project J2672, Shiawassee CountySolar Β· 200 MW Β· in study
- Replacing 160 MW of Solar with 80 MW of Solar and 90 MW of BESS; Bell SolarSolar + storage Β· 170 MW Β· in study
- Battery storage project J4122, Shiawassee CountyBattery storage Β· 150 MW Β· in study
- Solar project J796, Shiawassee CountySolar Β· 239 MW Β· built
- Onshore wind project J3640, Shiawassee CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project J602, Shiawassee CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J195, Shiawassee CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J187, Shiawassee CountyOnshore wind Β· 198 MW Β· withdrawn
- Solar project J1089, Shiawassee CountySolar Β· 170 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem