United States βΊ Grid βΊ Interconnection queues βΊ Louisiana
SOLAR Β· MISOSolar project J1452, Red River Parish County
Solar project J1452, Red River Parish County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Red River Parish County, Louisiana, connecting to CLECO POWER.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedMar 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1452
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CLECO POWER
- Connection point (POI)
- Carroll - Mansfield 138 kV Line Tap
- Location
- Red River Parish County, Louisiana
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- October 2022
- Withdrawn
- March 2021
Location
Marker shows the centre of Red River Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in Red River Parish County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem