πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

ONSHORE WIND Β· MISO

Onshore wind project J1404, Sunflower County

Onshore wind project J1404, Sunflower County is a 167 MW onshore wind request withdrawn in the MISO interconnection queue, in Sunflower County, Mississippi, connecting to ENTERGY MISSISSIPPI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedJul 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1404
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI
Connection point (POI)
Drew 115kV Substation
Location
Sunflower County, Mississippi
Technology
Wind: 167 MW
Total requested
167 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
October 2022
Withdrawn
July 2020

Location

Marker shows the centre of Sunflower County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Sunflower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem