OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Rhode Island, ISO-NE

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9110.2 GW
Active in queue982 MW3 requests
Agreement signed982 MW3 requests
Withdrawn9110.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

91 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore Wind
Offshore wind
1,200 MWWithdrawn / abandoned RIISO-NE Apr 2024target 2031
Clear River
Gas
1,030 MWWithdrawn / abandoned Providence, RIISO-NE Jan 2015target 2022
Combined Cycle
Gas
870 MWWithdrawn / abandoned Newport, RIISO-NE May 2015target 2020
Wind
Onshore wind
536 MWWithdrawn / abandoned Washington, RIISO-NE Feb 2010target 2015
Exciter Upgrades
Gas
492 MWWithdrawn / abandoned Providence, RIISO-NE Jun 2010target 2011
Wind
Onshore wind
450 MWWithdrawn / abandoned RIISO-NE May 2008target 2013
Battery Storage
Battery storage
415 MWWithdrawn / abandoned Providence, RIISO-NE Jun 2024target 2027
Wind
Onshore wind
385 MWWithdrawn / abandoned Washington, RIISO-NE May 2008target 2012
Offshore Wind
Offshore wind
352 MWWithdrawn / abandoned RIISO-NE Sep 2018target 2024
Combined Cycle( see # 201)
Gas
320 MWWithdrawn / abandoned Providence, RIISO-NE Aug 2006target 2012
Battery Storage
Battery storage
313 MWWithdrawn / abandoned Washington, RIISO-NE Jun 2024target 2027
Battery Storage
Battery storage
305 MWWithdrawn / abandoned Providence, RIISO-NE Oct 2022target 2027
Combined Cycle
Gas
285 MWWithdrawn / abandoned Newport, RIISO-NE Dec 2007target 2014
Combustion Turbine Generator
Gas
238 MWWithdrawn / abandoned Providence, RIISO-NE Feb 2015target 2020
Combustion Turbine (Alt to Q523)
Gas
234 MWWithdrawn / abandoned Providence, RIISO-NE Feb 2015target 2019
Combustion Turbine
Gas
227 MWWithdrawn / abandoned Providence, RIISO-NE Feb 2015target 2019
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Kent, RIISO-NE Mar 2021target 2023
Battery Storage
Battery storage
180 MWWithdrawn / abandoned Washington, RIISO-NE Apr 2019target 2023
Battery Storage
Battery storage
170 MWWithdrawn / abandoned Providence, RIISO-NE Dec 2021target 2024
Offshore Wind Increase (Q781)
Offshore wind
167 MWWithdrawn / abandoned RIISO-NE Sep 2019target 2023
Battery Storage
Battery storage
166 MWWithdrawn / abandoned Providence, RIISO-NE May 2024target 2028
Converts QP 164 to combined cycle facility and inc
Gas
162 MWWithdrawn / abandoned Providence, RIISO-NE Feb 2007target 2014
Internal Combustion
Gas
119 MWWithdrawn / abandoned Newport, RIISO-NE Mar 2015target 2019
Battery Storage
Battery storage
109 MWWithdrawn / abandoned Providence, RIISO-NE Jun 2023target 2027
Battery Storage
Battery storage
108 MWWithdrawn / abandoned Providence, RIISO-NE Dec 2023target 2027
Battery Storage
Battery storage
108 MWWithdrawn / abandoned Providence, RIISO-NE Jun 2024target 2027
Battery Storage
Battery storage
102 MWWithdrawn / abandoned Providence, RIISO-NE May 2023target 2026
Battery Storage
Battery storage
62.8 MWWithdrawn / abandoned Kent, RIISO-NE Mar 2022target 2025
Solar (QF)
Solar
56.5 MWWithdrawn / abandoned Washington, RIISO-NE Oct 2018target 2021
Battery Storage
Battery storage
55.0 MWWithdrawn / abandoned Providence, RIISO-NE Oct 2022target 2027
Battery Storage
Battery storage
50.4 MWWithdrawn / abandoned Providence, RIISO-NE Jan 2021target 2022
Kent County - NG WRI DG Area Study #2 >5 MW
Solar
49.8 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2025
Wood River Substation - Western RI DER Study #3
Solar
49.0 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2024target 2026
Solar (QF)
Solar
40.0 MWWithdrawn / abandoned Washington, RIISO-NE Oct 2018target 2025
Combined Cycle Upgrade
Gas
40.0 MWWithdrawn / abandoned Providence, RIISO-NE Apr 2016target 2020
Battery Storage
Battery storage
40.0 MWWithdrawn / abandoned Kent, RIISO-NE Oct 2022target 2027
Wood River - NG WRI DG Area Study #2 >5 MW
Solar
34.4 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2025
Solar
Solar
30.0 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2018target 2020
Wind
Onshore wind
28.8 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2009target 2012
Battery Storage
Battery storage
27.4 MWWithdrawn / abandoned Providence, RIISO-NE Mar 2022target 2025
Combined Cycle
Gas
27.0 MWWithdrawn / abandoned Providence, RIISO-NE May 2008target 2012
Land Fill Gas
Other
25.0 MWWithdrawn / abandoned Providence, RIISO-NE Jan 2006target 2007
Kent County Substation - Western RI DER Study #3
Solar
21.7 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2024target 2026
Combined Cycle Uprate
Gas
21.1 MWWithdrawn / abandoned Providence, RIISO-NE Apr 2016target 2016
Wind
Onshore wind
20.0 MWWithdrawn / abandoned Washington, RIISO-NE Feb 2009target 2012
Kent County - NG WRI DG Area Study #2 <5 MW
Solar
13.5 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2022
Solar
Solar
11.0 MWWithdrawn / abandoned Newport, RIISO-NE Dec 2018target 2025
Kent County Substation - NG Western RI DG Area Study
Solar
10.4 MWWithdrawn / abandoned Kent, RIISO-NE Mar 2020target 2021
Solar (QF)
Solar
10.0 MWWithdrawn / abandoned Washington, RIISO-NE Oct 2018target 2025
Solar
Solar
10.0 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2018target 2019
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)