Requests shown1,986447.3 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,986 requests · page 9 of 40
ProjectCapacityStatusLocationRegionQueuedOnline
Riverbend Solar SLF
Solar + storage · Riverbend Renewables, LLC
302 MWIn study Falls, TXERCOT Mar 2023target 2027
Sunburst Solar
Solar + storage · Indigo Solar, LLC
302 MWIn study San Patricio, TXERCOT Oct 2024target 2029
Tapaderos Solar
Solar + storage · Tapaderos Solar, LLC
302 MWIn study Young, TXERCOT Nov 2024target 2028
El Sauz Ranch
Onshore wind · El Sauz Ranch Wind, LLC
302 MWAgreement signed Willacy, TXERCOT Jun 2018target 2026
Crater BESS
Battery storage · BRP Crater BESS LLC
302 MWIn study Howard, TXERCOT May 2020target 2028
Ciervo Wind
Onshore wind · RWE Clean Energy Development, LLC
302 MWIn study Jim Hogg, TXERCOT Dec 2024target 2028
Pine Forest Solar
Solar · Pine Forest Solar I, LLC
302 MWAgreement signed Hopkins, TXERCOT Oct 2018target 2025
Rubicon Power BESS
Battery storage · Rubicon Power LLC
301 MWIn study Brazoria, TXERCOT Nov 2023target 2026
Quela BESS
Battery storage · BRP Quela BESS LLC
301 MWIn study Bexar, TXERCOT Sep 2020target 2027
Gulf Gateway Storage One
Solar + storage · Gulf Gateway Storage, LLC
301 MWIn study San Patricio, TXERCOT Aug 2025target 2027
Gulf Gateway Solar One
Solar + storage · Gulf Gateway Solar, LLC
301 MWIn study San Patricio, TXERCOT Apr 2025target 2027
Cenizo Solar
Solar · Renew Development Holdco, LLC
301 MWIn study Webb, TXERCOT Nov 2025target 2029
Themisto Solar
Solar · Themisto Solar, LLC
301 MWIn study Nolan, TXERCOT Feb 2024target 2028
Seine BESS
Battery storage · BRP Seine BESS LLC
301 MWAgreement signed Foard, TXERCOT Dec 2020target 2027
Cernan BESS
Battery storage · Scarlet BESS LLC
301 MWIn study Wharton, TXERCOT Feb 2025target 2027
Palomino Solar
Solar + storage · Palomino Renewables
301 MWIn study Hopkins, TXERCOT Oct 2024target 2028
Horseshoe Bend Solar
Solar · Clenera
301 MWIn study Brown, TXERCOT Jun 2017target 2027
Sweetheart Solar
Solar + storage · Sweetheart Energy, LLC
301 MWIn study Young, TXERCOT Aug 2025target 2029
Prairie Branch Solar
Solar + storage · Prairie Branch Solar
301 MWIn study Montague, TXERCOT Sep 2025target 2028
Blue Spring Solar
Solar · Flat Creek Solar, LLC
301 MWIn study Haskell, TXERCOT Oct 2025target 2028
Sundance Solar
Solar · Sundance Solar, LLC
301 MWIn study Knox, TXERCOT Apr 2025target 2029
Apricot Sun Storage
Solar + storage · Apricot Sun Energy Center, LLC
301 MWIn study Duval, TXERCOT Apr 2025target 2029
Acker BESS
Battery storage · Ogallala BESS LLC
301 MWAgreement signed Castro, TXERCOT Jun 2023target 2028
Barranca Wind 1
Onshore wind · Barranca Wind Energy, LLC
301 MWIn study Jim Hogg, TXERCOT Jul 2025target 2028
Great Rock BESS
Battery storage · Black Mountain Energy Storage II
301 MWAgreement signed Leon, TXERCOT Nov 2022target 2027
Jaguar Solar
Solar + storage · PP Jaguar Solar LLC
301 MWAgreement signed Mclennan, TXERCOT Mar 2021target 2027
Delilah Solar 1
Solar · Delilah Solar Energy LLC
300 MWAgreement signed Lamar, TXERCOT Nov 2018target 2026
Pachanga Wind
Onshore wind · Pachanga Wind LLC
300 MWIn study Cameron, TXERCOT Feb 2021target 2027
Bendito Wind
Onshore wind · Bendito Wind Farm, LLC
300 MWIn study Webb, TXERCOT Jul 2025target 2029
Photo Solar 2
Solar + storage · CED Development Inc.
300 MWIn study Uvalde, TXERCOT Sep 2022target 2027
Arroyo Del Bisonte Solar
Solar · Sunchase Power
300 MWPaused / redesign Wharton, TXERCOT May 2018target 2021
Pierce Wind
Onshore wind
300 MWPaused / redesign Wharton, TXERCOT Jan 2018
SP Jaguar BESS
Other · PP Jaguar BESS LLC
300 MWPaused / redesign Mclennan, TXERCOT Mar 20212025
Mandolin Solar SLF
Solar + storage · Mandolin Solar Project, LLC
300 MWIn study Starr, TXERCOT Jul 2024target 2029
Selenite Springs Solar
Solar · Selenite Springs Solar, LLC
300 MWIn study Pecos, TXERCOT Apr 2025target 2028
Diversion Wind
Onshore wind
300 MWPaused / redesign Baylor, TXERCOT Sep 2019target 2024
Gardner Draw Solar
Solar · RWE Clean Energy Development, LLC
300 MWAgreement signed Glasscock, TXERCOT Oct 2024target 2027
Peach Creek Solar
Solar · Acciona Energy USA Global LLC
300 MWIn study Wharton, TXERCOT Dec 2024target 2028
Wisdom Solar SLF
Solar + storage · Wisdom Green Energy LLC
299 MWIn study Pecos, TXERCOT Feb 2025target 2027
Board Creek Wind
Onshore wind · Limestone Wind Project, LLC
299 MWAgreement signed Navarro, TXERCOT Apr 2019target 2026
Barranca Wind 2
Onshore wind · Barranca Wind Energy, LLC
299 MWIn study Jim Hogg, TXERCOT Jul 2025target 2028
Camino Ranch Storage SLF
Solar + storage · Camino Solar Ranch, LLC
298 MWIn study Houston, TXERCOT Oct 2022target 2028
Palo Verde Wind
Wind + storage · RWE Clean Energy Development, LLC
298 MWIn study San Patricio, TXERCOT Apr 2024target 2027
Aquilla Lake 3 Wind
Onshore wind · Aquilla Lake 3 Wind
297 MWAgreement signed Hill, TXERCOT Mar 2021target 2027
Prairie Hill Wind
Onshore wind · Prairie Hill LLC
297 MWAgreement signed Mclennan, TXERCOT Jun 20172020
Camino Ranch Solar SLF
Solar + storage · Camino Ranch Solar Project LLC
296 MWIn study Houston, TXERCOT Oct 2022target 2028
Fortuna Wind
Onshore wind · RWE Renewables Development, LLC
295 MWAgreement signed Jack, TXERCOT Mar 2020target 2026
Columbine Wind
Onshore wind · Wilson Wind LLC
295 MWIn study Gonzales, TXERCOT Feb 2025target 2029
Sanders Hollow Energy Center
Onshore wind · Sanders Hollow Energy Center, LLC
293 MWIn study Dickens, TXERCOT Oct 2024target 2028
Windjammer Windpower
Onshore wind · Windjammer Windpower, LLC
293 MWAgreement signed Glasscock, TXERCOT Sep 2024target 2028
Page 9 of 40

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)