United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 8
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AG1-178, Sussex County Solar · Cabin Point Solar, LLC |
500 MW | Withdrawn / abandoned |
| Gas project G06_W44, Monongalia County Gas |
500 MW | Withdrawn / abandoned |
| Solar + storage project AE1-216, White County Solar + storage |
500 MW | Withdrawn / abandoned |
| Gas project H14_W67 Gas |
500 MW | Withdrawn / abandoned |
| Gas project H25, Somerset County Gas |
500 MW | Withdrawn / abandoned |
| Solar project AD2-197, Greensville County Solar |
500 MW | Withdrawn / abandoned |
| Battery storage project AH1-758, Adams County Battery storage · Cardinal Energy Storage East, LLC |
500 MW | Withdrawn / abandoned |
| Other project X4-038 Other |
500 MW | Withdrawn / abandoned |
| Gas project B12, Montgomery County Gas |
500 MW | Withdrawn / abandoned |
| Onshore wind project AE1-193, Henry County Onshore wind |
500 MW | Withdrawn / abandoned |
| Gas project D23, Indiana County Gas |
500 MW | Withdrawn / abandoned |
| Gas project B42, Luzerne County Gas |
500 MW | Withdrawn / abandoned |
| Battery storage project AH1-757, Union County Battery storage · Cardinal Energy Storage East, LLC |
500 MW | Withdrawn / abandoned |
| Onshore wind project V3-003, Clinton County Onshore wind |
500 MW | Withdrawn / abandoned |
| Gas project D24, Tioga County Gas |
500 MW | Withdrawn / abandoned |
| Other project X4-033 Other |
500 MW | Withdrawn / abandoned |
| Onshore wind project S62, Lasalle County Onshore wind |
500 MW | Withdrawn / abandoned |
| Other project X4-037 Other |
500 MW | Withdrawn / abandoned |
| Onshore wind project AD1-137, Benton County Onshore wind |
500 MW | Withdrawn / abandoned |
| Gas project B50, Erie County Gas |
500 MW | Withdrawn / abandoned |
| Emerson Creek Wind Farm Onshore wind |
500 MW | Withdrawn / abandoned |
| Gas project A56, Salem County Gas |
500 MW | Withdrawn / abandoned |
| Onshore wind project AE1-194, Will County Onshore wind |
500 MW | Withdrawn / abandoned |
| Other project T178 Other |
500 MW | Withdrawn / abandoned |
| Gas project B32, Dauphin County Gas |
500 MW | Withdrawn / abandoned |
| Other project W3-065 Other |
500 MW | Withdrawn / abandoned |
| Gas project A14, Middlesex County Gas |
500 MW | Withdrawn / abandoned |
| Gas project G30_W55 Gas |
500 MW | Withdrawn / abandoned |
| Battery storage project AH1-754, Muskingum County Battery storage · Cardinal Energy Storage East, LLC |
500 MW | Withdrawn / abandoned |
| Gas project G06_W45, Harrison County Gas |
500 MW | Withdrawn / abandoned |
| Onshore wind project AE1-197, White County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project U2-058, Christian County Onshore wind |
500 MW | Withdrawn / abandoned |
| Solar project AG2-655, Grant County Solar · Mount Storm Solar, LLC |
500 MW | Withdrawn / abandoned |
| Gas project H11, Gloucester County Gas |
500 MW | Withdrawn / abandoned |
| Solar project AE1-068, Greensville County Solar |
500 MW | Withdrawn / abandoned |
| Gas project C06, Luzerne County Gas |
500 MW | Withdrawn / abandoned |
| Gas project B51, Indiana County Gas |
500 MW | Withdrawn / abandoned |
| Battery storage project AG1-298, Cook County Battery storage · Big Shoulders Storage LLC |
500 MW | Withdrawn / abandoned |
| Other project T177 Other |
500 MW | Withdrawn / abandoned |
| Suburban Landfill Other |
500 MW | Withdrawn / abandoned |
| Offshore wind project W3-043, City Of Virginia Beach County Offshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project AE1-195, Will County Onshore wind |
500 MW | Withdrawn / abandoned |
| Battery storage project AG2-375, Hancock County Battery storage · Foster Energy Storage LLC |
500 MW | Withdrawn / abandoned |
| Onshore wind project W3-005, Huron County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project U1-024, Warren County Onshore wind |
500 MW | Withdrawn / abandoned |
| Hydro project AE1-058, Schuylkill County Hydro |
500 MW | Withdrawn / abandoned |
| Other project T176 Other |
500 MW | Withdrawn / abandoned |
| Gas project E08, Luzerne County Gas |
500 MW | Withdrawn / abandoned |
| Pleasant Ridge Wind Farm Onshore wind |
500 MW | Withdrawn / abandoned |
| Battery storage project AG2-475, Charles City County Battery storage |
500 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)