OTHER Β· PJM

Suburban Landfill

Suburban Landfill is a 500 MW other request withdrawn in the PJM interconnection queue, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2009 (completed)
  2. Withdrawn / abandonedFeb 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
V4-008
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Braidwood 1-AD Hub
Technology
Other: 500 MW
Total requested
500 MW
Service type
Energy only (ERIS)
Study phase
Available studies: System Impact Study
Queue status
Withdrawn
Entered queue
12 November 2009
Withdrawn
February 2012

Location

No county location in the queue data.