United States βΊ Grid βΊ Interconnection queues
OTHER Β· PJMSuburban Landfill
Suburban Landfill is a 500 MW other request withdrawn in the PJM interconnection queue, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2009 (completed)
- Withdrawn / abandonedFeb 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- V4-008
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Braidwood 1-AD Hub
- Technology
- Other: 500 MW
- Total requested
- 500 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 12 November 2009
- Withdrawn
- February 2012
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem