Onshore wind interconnection queue in the USA — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown826200.1 GW
Active in queue200.1 GW826 requests
Agreement signed49.9 GW242 requests
Withdrawn4,524860.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

826 requests · page 7 of 17
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J848, Christian County
Onshore wind
250 MWUnder construction Christian, ILMISO Jun 2017target 2021
Onshore wind project 438, Stillwater County
Onshore wind
250 MWPaused / redesign Stillwater, MTWest Jan 2023target 2026
Onshore wind project GEN-2024-042, Floyd County
Onshore wind
250 MWIn study Floyd, TXSPP Oct 2024target 2028
Onshore wind project GEN-2024-043, Roosevelt County
Onshore wind
250 MWIn study Roosevelt, NMSPP Oct 2024target 2029
Onshore wind project IA-PNM-2023-01, Cibola County
Onshore wind
250 MWIn study Cibola, NMWest Oct 2022target 2025
Onshore wind project J1432, Clinton County
Onshore wind
250 MWAgreement signed Clinton, IAMISO Apr 2019target 2025
Onshore wind project GEN-2024-291, Pittsburg County
Onshore wind
250 MWIn study Pittsburg, OKSPP Mar 2025target 2030
Onshore wind project 23-227, Jefferson County
Onshore wind
250 MWIn study Jefferson, ORWest Mar 2023target 2029
Onshore wind project GEN-2024-135, Woods County
Onshore wind
250 MWIn study Woods, OKSPP Mar 2025target 2031
Onshore wind project J3326, Lyon County
Onshore wind
250 MWIn study Lyon, MNMISO Apr 2024target 2028
Onshore wind project GEN-2024-041, Floyd County
Onshore wind
250 MWIn study Floyd, TXSPP Oct 2024target 2029
Onshore wind project G0294, Columbia County
Onshore wind
250 MWAgreement signed Columbia, WAWest Oct 2007target 2011
Onshore wind project GEN-2024-145, Dallam County
Onshore wind
250 MWIn study Dallam, TXSPP Mar 2025target 2032
Onshore wind project J1485, Deuel County
Onshore wind
250 MWIn study Deuel, SDMISO Apr 2019target 2022
Onshore wind project GEN-2024-143, Dallam County
Onshore wind
250 MWIn study Dallam, TXSPP Mar 2025target 2032
Onshore wind project GI-TC-2024-15, Laramie County
Onshore wind
250 MWAgreement signed Laramie, WYWest May 2024target 2029
Onshore wind project GEN-2024-134, Woods County
Onshore wind
250 MWIn study Woods, OKSPP Mar 2025target 2031
Onshore wind project G0559, Benton County
Onshore wind
250 MWIn study Benton, WAWest Mar 2017target 2019
Onshore wind project GEN-2024-285, Clark County
Onshore wind
250 MWIn study Clark, SDSPP Mar 2025target 2030
Onshore wind project GI-2007-13, Lincoln County
Onshore wind
250 MWAgreement signed Lincoln, COWest Nov 2007target 2009
Onshore wind project J3639, Columbia County
Onshore wind
250 MWIn study Columbia, WIMISO Apr 2024target 2028
Onshore wind project GEN-2017-134, Oklahoma County
Onshore wind
250 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Onshore wind project IA-PNM-2025-18, Torrance County
Onshore wind
250 MWIn study Torrance, NMWest Mar 2025target 2028
Onshore wind project J3865, Shiawassee County
Onshore wind
250 MWIn study Shiawassee, MIMISO Dec 2024target 2028
Onshore wind project J3750, Mercer County
Onshore wind
250 MWIn study Mercer, ILMISO Apr 2024target 2028
Onshore wind project 23-228, Jefferson County
Onshore wind
250 MWIn study Jefferson, ORWest Mar 2023target 2029
Onshore wind project J2275, Peoria County
Onshore wind
250 MWIn study Peoria, ILMISO Mar 2022target 2025
Onshore wind project MPC03800, Eddy County
Onshore wind
250 MWAgreement signed Eddy, NDMISO Feb 2019target 2027
Onshore wind project J3929, Audrain County
Onshore wind
250 MWIn study Audrain, MOMISO Jan 2025target 2030
Onshore wind project J1040, Mcintosh County
Onshore wind
250 MWUnder construction Mcintosh, NDMISO Mar 2018target 2023
Onshore wind project 23-231, Jefferson County
Onshore wind
250 MWIn study Jefferson, ORWest Mar 2023target 2027
Onshore wind project J4018, Ford County
Onshore wind
250 MWIn study Ford, ILMISO May 2025target 2029
Onshore wind project GI-2007-12, El Paso County
Onshore wind
250 MWAgreement signed El Paso, COWest Nov 2007target 2010
Onshore wind project GEN-2024-235, Payne County
Onshore wind
250 MWIn study Payne, OKSPP Mar 2025target 2029
Onshore wind project GEN-2017-201, Wayne County
Onshore wind
250 MWAgreement signed Wayne, NESPP Nov 2017target 2028
Onshore wind project G0295, Columbia County
Onshore wind
250 MWAgreement signed Columbia, WAWest Oct 2007target 2011
Onshore wind project G0974, Wasco County
Onshore wind
250 MWIn study Wasco, ORWest Oct 2023target 2029
Onshore wind project GEN-2021-069, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project GEN-2024-193, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Onshore wind project GEN-2024-194, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Onshore wind project GEN-2021-068, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project J3275, Benton County
Onshore wind
249 MWIn study Benton, MNMISO Apr 2024target 2028
Grandview 5 W
Onshore wind · Eon
249 MWPaused / redesign Gray, TXERCOT Jul 2006target 2022
Straight Spur Wind
Onshore wind · ENGIE IR Holdings LLC
247 MWIn study Andrews, TXERCOT Dec 2024target 2029
Onshore wind project GI-95, Dade County
Onshore wind
247 MWAgreement signed Dade, MOSoutheast Dec 2020target 2026
EC500W Project
Onshore wind
247 MWAgreement signed Chaves, NMWest Jul 2017target 2020
Onshore wind project J476, Atchison County
Onshore wind
246 MWAgreement signed Atchison, MOMISO Sep 2015target 2021
Coyote Wind
Onshore wind · Coyote Wind
243 MWAgreement signed Scurry, TXERCOT Apr 20152021
Onshore wind project Q458, Navajo County
Onshore wind
242 MWIn study Navajo, AZWest Mar 2022target 2026
Lutum Wind
Onshore wind · RWE
242 MWIn study Clay, TXERCOT Sep 2017target 2027
Page 7 of 17

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)