United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2025 requests) — page 6
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 315, Florence County Gas |
149 MW | Withdrawn / abandoned |
| Solar + storage project 25-IC-1352, Henry County Solar + storage |
148 MW | Withdrawn / abandoned |
| Solar project GEN-2024-358, Lyon County Solar |
145 MW | Withdrawn / abandoned |
| Battery storage project J3906, Stoddard County Battery storage |
140 MW | Withdrawn / abandoned |
| Battery storage project GEN-2024-169, Creek County Battery storage |
140 MW | Withdrawn / abandoned |
| Solar project AG2-188, Cumberland County Solar · Bear Creek Solar, LLC |
140 MW | Withdrawn / abandoned |
| Solar project J4015, Mason County Solar |
136 MW | Withdrawn / abandoned |
| Solar + storage project 25-IC-1359, Pearl River County Solar + storage |
130 MW | Withdrawn / abandoned |
| Solar project GEN-2024-315, Haskell County Solar |
130 MW | Withdrawn / abandoned |
| Battery storage project GEN-2024-174, Mercer County Battery storage |
130 MW | Withdrawn / abandoned |
| Solar + storage project AH1-539, Hardin County Solar + storage · Riverlake Energy, LLC |
129 MW | Withdrawn / abandoned |
| Battery storage project J4060, Mcleod County Battery storage |
129 MW | Withdrawn / abandoned |
| Onshore wind project CS25-02, Adams County Onshore wind |
126 MW | Withdrawn / abandoned |
| Solar project J2733, Lawrence County Solar |
126 MW | Withdrawn / abandoned |
| Solar project AG2-403, Hardy County Solar · Old Fields Solar, LLC |
125 MW | Withdrawn / abandoned |
| Solar project J3938, Marshall County Solar |
123 MW | Withdrawn / abandoned |
| Solar project AG2-449, Rush County Solar · Salmon Solar LLC |
120 MW | Withdrawn / abandoned |
| Onshore wind project CS25-01, Spokane County Onshore wind |
120 MW | Withdrawn / abandoned |
| Solar project AH1-408, Brunswick County Solar · SR Brunswick, LLC |
120 MW | Withdrawn / abandoned |
| Solar + storage project GEN-2024-214, Hempstead County Solar + storage |
120 MW | Withdrawn / abandoned |
| Southern Star Solar SLF Solar · Southern Star Solar Project, LLC |
116 MW | Withdrawn / abandoned |
| Solar project AG2-162, Rush County Solar · Salmon Solar LLC |
115 MW | Withdrawn / abandoned |
| Solar project J4035, Greene County Solar |
113 MW | Withdrawn / abandoned |
| Solar + storage project 25-IC-1353, Mobile County Solar + storage |
112 MW | Withdrawn / abandoned |
| Other project C01-1013, Charles County Other · Chalk Point Steam, LLC |
108 MW | Withdrawn / abandoned |
| Battery storage project Q2509, Pinal County Battery storage |
105 MW | Withdrawn / abandoned |
| Cycle Storage Battery storage · Grenergy USA |
105 MW | Withdrawn / abandoned |
| swoose BESS III Battery storage · Tempus power management LLC |
104 MW | Withdrawn / abandoned |
| Highline BESS Battery storage · Highline BESS |
103 MW | Withdrawn / abandoned |
| Winslow Storage Battery storage · Winslow Storage, LLC |
101 MW | Withdrawn / abandoned |
| Nittany North Solar Solar + storage · Invenergy Solar Project Development LLC |
100 MW | Withdrawn / abandoned |
| Solar project GEN-2024-148, Lamb County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AH1-102, Indiana County Solar · Clarke Run Solar LLC |
100 MW | Withdrawn / abandoned |
| Other project PP00032, Wake County Other |
100 MW | Withdrawn / abandoned |
| Solar + storage project AG2-093, Prince George County Solar + storage · Admiral Solar LLC |
100 MW | Withdrawn / abandoned |
| Michiana Solar Solar · ibV Energy Partners LLC |
100 MW | Withdrawn / abandoned |
| Battery storage project AG2-310, Roanoke County Battery storage · Matt Funk Storage, LLC |
100 MW | Withdrawn / abandoned |
| Solar project GEN-2024-105, Ford County Solar |
100 MW | Withdrawn / abandoned |
| Solar + storage project AG2-575, Dekalb County Solar + storage · Red Maple Solar, LLC |
100 MW | Withdrawn / abandoned |
| Seward-Glory 115 kV Solar · Clark Run Solar LLC |
100 MW | Withdrawn / abandoned |
| Battery storage project AH1-323, City Of Suffolk County Battery storage · Invenergy Storage Development LLC |
100 MW | Withdrawn / abandoned |
| Battery storage project AH1-157, York County Battery storage · Delorean Power LLC dba Lightshift Energy |
100 MW | Withdrawn / abandoned |
| Battery storage project AH1-729, Loudoun County Battery storage · GSP Sterling Project I, LLC |
100 MW | Withdrawn / abandoned |
| Hampton BESS 3 Battery storage · Delorean Power LLC dba Lightshift Energy |
100 MW | Withdrawn / abandoned |
| Solar project AH1-644 Solar · Kentucky Power Company |
100 MW | Withdrawn / abandoned |
| Solar project AG2-615, Allegany County Solar · Squirrel Run Solar, L.L.C. |
100 MW | Withdrawn / abandoned |
| Battery storage project GI-SISS-2025-01, Kit Carson County Battery storage |
100 MW | Withdrawn / abandoned |
| Scotland Solar Solar · Scotland Solar, LLC |
100 MW | Withdrawn / abandoned |
| Energix Westmoreland LLC Solar · Energix Westmoreland, LLC |
100 MW | Withdrawn / abandoned |
| Sugar Solar LLC Solar · Sugar Solar, LLC |
100 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- SPP (Southwest Power Pool)99 · 26.5 GW
- MISO (Midcontinent)62 · 22.5 GW
- West (non-ISO utilities)75 · 20.5 GW
- PJM (Mid-Atlantic, Midwest)160 · 15.8 GW
- Southeast (non-ISO utilities)44 · 8,611 MW
- ERCOT (Texas)17 · 2,075 MW
- NYISO (New York)16 · 1,089 MW
- ISO-NE (New England)1 · 5.0 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)