Withdrawn queue requests in the USA (2025 requests) — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown47497.1 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

474 requests · page 6 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 315, Florence County
Gas
149 MWWithdrawn / abandoned Florence, SCSoutheast Jun 2025target 2029
Solar + storage project 25-IC-1352, Henry County
Solar + storage
148 MWWithdrawn / abandoned Henry, ALSoutheast Apr 2025
Solar project GEN-2024-358, Lyon County
Solar
145 MWWithdrawn / abandoned Lyon, KSSPP Mar 2025target 2028
Battery storage project J3906, Stoddard County
Battery storage
140 MWWithdrawn / abandoned Stoddard, MOMISO Mar 2025target 2030
Battery storage project GEN-2024-169, Creek County
Battery storage
140 MWWithdrawn / abandoned Creek, OKSPP Mar 2025target 2028
Solar project AG2-188, Cumberland County
Solar · Bear Creek Solar, LLC
140 MWWithdrawn / abandoned Cumberland, VAPJM Feb 2025target 2024
Solar project J4015, Mason County
Solar
136 MWWithdrawn / abandoned Mason, ILMISO May 2025target 2030
Solar + storage project 25-IC-1359, Pearl River County
Solar + storage
130 MWWithdrawn / abandoned Pearl River, MSSoutheast Apr 2025
Solar project GEN-2024-315, Haskell County
Solar
130 MWWithdrawn / abandoned Haskell, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-174, Mercer County
Battery storage
130 MWWithdrawn / abandoned Mercer, NDSPP Mar 2025target 2028
Solar + storage project AH1-539, Hardin County
Solar + storage · Riverlake Energy, LLC
129 MWWithdrawn / abandoned Hardin, OHPJM Mar 2025target 2025
Battery storage project J4060, Mcleod County
Battery storage
129 MWWithdrawn / abandoned Mcleod, MNMISO Aug 2025target 2030
Onshore wind project CS25-02, Adams County
Onshore wind
126 MWWithdrawn / abandoned Adams, WAWest Apr 2025target 2030
Solar project J2733, Lawrence County
Solar
126 MWWithdrawn / abandoned Lawrence, ARMISO Sep 2025target 2026
Solar project AG2-403, Hardy County
Solar · Old Fields Solar, LLC
125 MWWithdrawn / abandoned Hardy, WVPJM Jan 2025target 2024
Solar project J3938, Marshall County
Solar
123 MWWithdrawn / abandoned Marshall, INMISO Apr 2025target 2030
Solar project AG2-449, Rush County
Solar · Salmon Solar LLC
120 MWWithdrawn / abandoned Rush, INPJM Mar 2025target 2024
Onshore wind project CS25-01, Spokane County
Onshore wind
120 MWWithdrawn / abandoned Spokane, WAWest Apr 2025target 2028
Solar project AH1-408, Brunswick County
Solar · SR Brunswick, LLC
120 MWWithdrawn / abandoned Brunswick, VAPJM Feb 2025target 2024
Solar + storage project GEN-2024-214, Hempstead County
Solar + storage
120 MWWithdrawn / abandoned Hempstead, ARSPP Mar 2025target 2029
Southern Star Solar SLF
Solar · Southern Star Solar Project, LLC
116 MWWithdrawn / abandoned ERCOT Mar 2025target 2029
Solar project AG2-162, Rush County
Solar · Salmon Solar LLC
115 MWWithdrawn / abandoned Rush, INPJM Mar 2025target 2024
Solar project J4035, Greene County
Solar
113 MWWithdrawn / abandoned Greene, ARMISO Jun 2025target 2029
Solar + storage project 25-IC-1353, Mobile County
Solar + storage
112 MWWithdrawn / abandoned Mobile, ALSoutheast Apr 2025
Other project C01-1013, Charles County
Other · Chalk Point Steam, LLC
108 MWWithdrawn / abandoned Charles, MDPJM May 2025
Battery storage project Q2509, Pinal County
Battery storage
105 MWWithdrawn / abandoned Pinal, AZWest Feb 2025target 2028
Cycle Storage
Battery storage · Grenergy USA
105 MWWithdrawn / abandoned ERCOT Apr 2025target 2028
swoose BESS III
Battery storage · Tempus power management LLC
104 MWWithdrawn / abandoned ERCOT Jan 2025target 2026
Highline BESS
Battery storage · Highline BESS
103 MWWithdrawn / abandoned ERCOT Feb 2025target 2027
Winslow Storage
Battery storage · Winslow Storage, LLC
101 MWWithdrawn / abandoned ERCOT Feb 2025target 2029
Nittany North Solar
Solar + storage · Invenergy Solar Project Development LLC
100 MWWithdrawn / abandoned Centre, PAPJM Feb 2025target 2025
Solar project GEN-2024-148, Lamb County
Solar
100 MWWithdrawn / abandoned Lamb, TXSPP Mar 2025target 2032
Solar project AH1-102, Indiana County
Solar · Clarke Run Solar LLC
100 MWWithdrawn / abandoned Indiana, PAPJM Feb 2025target 2024
Other project PP00032, Wake County
Other
100 MWWithdrawn / abandoned Wake, NCSoutheast Jun 2025target 2028
Solar + storage project AG2-093, Prince George County
Solar + storage · Admiral Solar LLC
100 MWWithdrawn / abandoned Prince George, VAPJM Feb 2025target 2024
Michiana Solar
Solar · ibV Energy Partners LLC
100 MWWithdrawn / abandoned St. Joseph, INPJM Jan 2025target 2025
Battery storage project AG2-310, Roanoke County
Battery storage · Matt Funk Storage, LLC
100 MWWithdrawn / abandoned Roanoke, VAPJM Feb 2025target 2023
Solar project GEN-2024-105, Ford County
Solar
100 MWWithdrawn / abandoned Ford, KSSPP Mar 2025target 2031
Solar + storage project AG2-575, Dekalb County
Solar + storage · Red Maple Solar, LLC
100 MWWithdrawn / abandoned Dekalb, ILPJM Mar 2025target 2024
Seward-Glory 115 kV
Solar · Clark Run Solar LLC
100 MWWithdrawn / abandoned Indiana, PANYISO Sep 2025
Battery storage project AH1-323, City Of Suffolk County
Battery storage · Invenergy Storage Development LLC
100 MWWithdrawn / abandoned City Of Suffolk, VAPJM Feb 2025target 2025
Battery storage project AH1-157, York County
Battery storage · Delorean Power LLC dba Lightshift Energy
100 MWWithdrawn / abandoned York, VAPJM Feb 2025target 2025
Battery storage project AH1-729, Loudoun County
Battery storage · GSP Sterling Project I, LLC
100 MWWithdrawn / abandoned Loudoun, VAPJM Apr 2025
Hampton BESS 3
Battery storage · Delorean Power LLC dba Lightshift Energy
100 MWWithdrawn / abandoned City Of Hampton, VAPJM Feb 2025target 2023
Solar project AH1-644
Solar · Kentucky Power Company
100 MWWithdrawn / abandoned KYPJM Feb 2025target 2026
Solar project AG2-615, Allegany County
Solar · Squirrel Run Solar, L.L.C.
100 MWWithdrawn / abandoned Allegany, MDPJM Feb 2025target 2023
Battery storage project GI-SISS-2025-01, Kit Carson County
Battery storage
100 MWWithdrawn / abandoned Kit Carson, COWest Jun 2025target 2028
Scotland Solar
Solar · Scotland Solar, LLC
100 MWWithdrawn / abandoned Barren, KYPJM Mar 2025target 2025
Energix Westmoreland LLC
Solar · Energix Westmoreland, LLC
100 MWWithdrawn / abandoned Cumberland, VAPJM Feb 2025target 2024
Sugar Solar LLC
Solar · Sugar Solar, LLC
100 MWWithdrawn / abandoned Campbell, VAPJM Feb 2025target 2026
Page 6 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)