SOLAR + STORAGE · PJMNittany North Solar
Nittany North Solar is a 100 MW solar + storage request withdrawn in the PJM interconnection queue, in Centre County, Pennsylvania, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2025 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-313
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Developer
- Invenergy Solar Project Development LLC
- Connection point (POI)
- Moshannon-Milesburg 230 kV VII
- Location
- Centre County, Pennsylvania
- Technology
- Solar: 100 MW · Battery
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 14 February 2025
- Proposed online date
- December 2025
- Withdrawn
- December 2025
Location
Marker shows the centre of Centre County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Centre County
- Black Moshannon SolarSolar + storage · 95.0 MW · agreement signed
- MPG SolarSolar · 83.6 MW · agreement signed
- MPG SolarSolar · 78.4 MW · agreement signed
- Black Moshannon SolarSolar · 20.0 MW · agreement signed
- Black Moshannon SolarSolar · 20.0 MW · agreement signed
- Solar project AI2-154, Centre CountySolar · 24.0 MW · in study
- Solar + storage project AI2-439, Centre CountySolar + storage · 20.0 MW · in study
- Solar + storage project AI1-216, Centre CountySolar + storage · 20.0 MW · in study
- Solar + storage project AI1-214, Centre CountySolar + storage · 20.0 MW · in study
- Solar + storage project AI1-215, Centre CountySolar + storage · 20.0 MW · in study
- Solar + storage project AI2-440, Centre CountySolar + storage · 20.0 MW · in study
- Solar + storage project AI1-217, Centre CountySolar + storage · 17.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem