🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

SOLAR + STORAGE · PJM

Solar + storage project AI1-217, Centre County

Solar + storage project AI1-217, Centre County is a 17.0 MW solar + storage request in interconnection study in the PJM interconnection queue, in Centre County, Pennsylvania, connecting to PENELEC.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI1-217
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Philipsburg 115 kV VII
Location
Centre County, Pennsylvania
Technology
Solar: 17.0 MW · Battery
Total requested
17.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
10 September 2022
Proposed online date
June 2024

Location

Marker shows the centre of Centre County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Centre County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem