BATTERY STORAGE Β· PJM

Battery storage project AG2-310, Roanoke County

Battery storage project AG2-310, Roanoke County is a 100 MW battery storage request withdrawn in the PJM interconnection queue, in Roanoke County, Virginia, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-310
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Matt Funk Storage, LLC
Connection point (POI)
Matt Funk 138 kV
Location
Roanoke County, Virginia
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
3 February 2025
Proposed online date
December 2023
Withdrawn
December 2025

Location

Marker shows the centre of Roanoke County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Roanoke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem