πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

Highline BESS

Highline BESS is a 103 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2025 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26INR0629
Grid region
ERCOT (Texas)
Developer
Highline BESS
Connection point (POI)
38465 Stone Road 138kV
Technology
Battery: 103 MW
Total requested
103 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
14 February 2025
Proposed online date
April 2027

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem