United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

SOLAR + STORAGE Β· PJM

Solar + storage project AG2-575, Dekalb County

Solar + storage project AG2-575, Dekalb County is a 100 MW solar + storage request withdrawn in the PJM interconnection queue, in Dekalb County, Illinois, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-575
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Developer
Red Maple Solar, LLC
Connection point (POI)
Crego Rd. 138 kV
Location
Dekalb County, Illinois
Technology
Solar: 100 MW Β· Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
11 March 2025
Proposed online date
December 2024
Withdrawn
December 2025

Location

Marker shows the centre of Dekalb County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Dekalb County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem