πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

SOLAR Β· PJM

Solar project AG2-162, Rush County

Solar project AG2-162, Rush County is a 115 MW solar request withdrawn in the PJM interconnection queue, in Rush County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-162
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Salmon Solar LLC
Connection point (POI)
Jefferson-Greentown 765 kV
Location
Rush County, Indiana
Technology
Solar: 115 MW
Total requested
115 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
12 March 2025
Proposed online date
December 2024
Withdrawn
November 2025

Location

Marker shows the centre of Rush County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Rush County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem