SOLAR Β· MISO

Solar project J2746, Rush County

Solar project J2746, Rush County is a 70.0 MW solar request withdrawn in the MISO interconnection queue, in Rush County, Indiana, connecting to HOOSIER ENERGY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2746
Grid region
MISO (Midcontinent)
Utility / transmission owner
HOOSIER ENERGY
Connection point (POI)
Boyd - Sexton
Location
Rush County, Indiana
Technology
Solar: 70.0 MW
Total requested
70.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
July 2026
Withdrawn
March 2023

Location

Marker shows the centre of Rush County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Rush County