United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,646350.1 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,646 requests · page 6 of 33
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1214, Dane County
Solar
300 MWAgreement signed Dane, WIMISO Apr 2019target 2025
Onshore wind project J1025, Knox County
Onshore wind
300 MWAgreement signed Knox, MOMISO Mar 2018target 2025
Battery storage project J3525, Rock Island County
Battery storage
300 MWIn study Rock Island, ILMISO Apr 2024target 2028
Onshore wind project J3887, Montcalm County
Onshore wind
300 MWIn study Montcalm, MIMISO Jan 2025target 2030
Onshore wind project J3384, Big Stone County
Onshore wind
300 MWIn study Big Stone, MNMISO Apr 2024target 2028
Onshore wind project J3853, Iroquois County
Onshore wind
300 MWIn study Iroquois, ILMISO Dec 2024target 2029
Solar + storage project J3199, Adair County
Solar + storage
300 MWIn study Adair, MOMISO Sep 2022target 2026
Onshore wind project J3910, Newton County
Onshore wind
300 MWIn study Newton, INMISO Feb 2025target 2030
Solar project J2270, Sullivan County
Solar
300 MWIn study Sullivan, INMISO Aug 2021target 2024
Onshore wind project J1773, Lafayette County
Onshore wind
300 MWAgreement signed Lafayette, WIMISO Jun 2020target 2027
Battery storage project J3834, Gibson County
Battery storage
300 MWIn study Gibson, INMISO Sep 2024target 2026
Solar project J3758, Macon County
Solar
300 MWIn study Macon, MOMISO Apr 2024target 2028
Solar project J1308, Posey County
Solar
300 MWAgreement signed Posey, INMISO Apr 2019target 2024
Onshore wind project J4063, Knox County
Onshore wind
300 MWIn study Knox, INMISO Sep 2025target 2030
Onshore wind project J2436, Webster County
Onshore wind
300 MWIn study Webster, IAMISO Sep 2022target 2030
Onshore wind project J4195, Clinton County
Onshore wind
300 MWIn study Clinton, MIMISO Oct 2025target 2030
Solar project J4121, Washington County
Solar
300 MWIn study Washington, MSMISO Sep 2025target 2030
Onshore wind project J3960, Lac Qui Parle County
Onshore wind
300 MWIn study Lac Qui Parle, MNMISO Apr 2025target 2030
Solar + storage project J4012, Crittenden County
Solar + storage
300 MWIn study Crittenden, ARMISO May 2025target 2029
Onshore wind project J3672, Big Stone County
Onshore wind
300 MWIn study Big Stone, MNMISO Apr 2024target 2028
Battery storage project J4098, Lafayette Parish County
Battery storage
300 MWIn study Lafayette Parish, LAMISO Oct 2025target 2030
Onshore wind project J4112, Rock Island County
Onshore wind
300 MWIn study Rock Island, ILMISO Oct 2025target 2030
Battery storage project J4075, St. Landry Parish County
Battery storage
300 MWIn study St. Landry Parish, LAMISO Oct 2025target 2030
Solar project J2446, Dunn County
Solar
300 MWIn study Dunn, WIMISO Sep 2022target 2027
Wind + storage project J3027, Stark County
Wind + storage
300 MWIn study Stark, ILMISO Sep 2022target 2027
Onshore wind project MPC04000, Oliver County
Onshore wind
300 MWAgreement signed Oliver, NDMISO Apr 2019target 2023
Solar project J3669, Stevens County
Solar
300 MWIn study Stevens, MNMISO Apr 2024target 2028
Surplus; EAI.AECCO SWCT1
Other
300 MWIn study Lonoke, ARMISO Jun 2025target 2028
Battery storage project J3216, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Sep 2022target 2027
Battery storage project J3417, Macon County
Battery storage
300 MWIn study Macon, ILMISO Apr 2024target 2028
Battery storage project J2423, Columbia County
Battery storage
300 MWIn study Columbia, WIMISO Sep 2022target 2027
Solar project J3045, Orange County
Solar
300 MWIn study Orange, TXMISO Sep 2022target 2026
Onshore wind project J3280, Dickey County
Onshore wind
300 MWIn study Dickey, NDMISO Apr 2024target 2028
Solar project J4017, Blue Earth County
Solar
299 MWIn study Blue Earth, MNMISO May 2025target 2030
Solar project J3282, Mason County
Solar
297 MWIn study Mason, MIMISO Apr 2024target 2028
Solar project J4091, Otter Tail County
Solar
295 MWIn study Otter Tail, MNMISO Oct 2025target 2030
Onshore wind project J1557, Sanilac County
Onshore wind
293 MWAgreement signed Sanilac, MIMISO Jun 2020target 2026
Solar project J1743, Miami County
Solar
293 MWIn study Miami, INMISO Apr 2022target 2026
Solar project J3274, Ogemaw County
Solar
290 MWIn study Ogemaw, MIMISO Apr 2024target 2028
Onshore wind project J4006, Ringgold County
Onshore wind
290 MWIn study Ringgold, IAMISO May 2025target 2030
Onshore wind project J3902, Jefferson County
Onshore wind
289 MWIn study Jefferson, TXMISO Feb 2025target 2028
Solar + storage project J3002, Pine County
Solar + storage
288 MWIn study Pine, MNMISO Sep 2022target 2025
Solar project J3012, Coles County
Solar
287 MWIn study Coles, ILMISO Sep 2022target 2026
Solar project J3014, Rapides Parish County
Solar
280 MWIn study Rapides Parish, LAMISO Sep 2022target 2026
Sandcut Storage
Solar + storage · Hoosier Energy / Solvenz
280 MWIn study Vigo, INMISO Dec 2025target 2028
Solar project J813, Clay County
Solar
275 MWUnder construction Clay, ILMISO Jun 20172024
Onshore wind project J3564, Newton County
Onshore wind
275 MWIn study Newton, INMISO Apr 2024target 2028
Onshore wind project J3846, Newton County
Onshore wind
275 MWIn study Newton, INMISO Jan 2025target 2030
Solar project J1890, Sabine Parish County
Solar
270 MWIn study Sabine Parish, LAMISO Apr 2025target 2027
Solar project J3986, Liberty County
Solar
270 MWIn study Liberty, TXMISO Oct 2024target 2030
Page 6 of 33

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)