Withdrawn queue requests in West (non-ISO utilities) — page 56

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 56 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project IA-PNM-2021-11, San Juan County
Solar + storage
100 MWWithdrawn / abandoned San Juan, NMWest Jul 2021target 2025
Solar + storage project C2-128, Yakima County
Solar + storage
100 MWWithdrawn / abandoned Yakima, WAWest May 2022target 2025
Onshore wind project G0422, Wheeler County
Onshore wind
100 MWWithdrawn / abandoned Wheeler, ORWest Apr 2010target 2013
Coal project BHBE G6, Campbell County
Coal
100 MWWithdrawn / abandoned Campbell, SDWest Jul 2006target 2011
Onshore wind project 32, Whitman County
Onshore wind
100 MWWithdrawn / abandoned Whitman, WAWest Feb 2011target 2012
Solar + storage project 1218, Beaver County
Solar + storage
100 MWWithdrawn / abandoned Beaver, UTWest Apr 2020target 2023
Solar project 55, Pima County
Solar
100 MWWithdrawn / abandoned Pima, AZWest Jan 2017target 2018
Solar + storage project Company IS, Douglas County
Solar + storage
100 MWWithdrawn / abandoned Douglas, NVWest Sep 2018target 2022
Onshore wind project 48, Adams County
Onshore wind
100 MWWithdrawn / abandoned Adams, WAWest Jan 2016target 2016
Battery storage project 144, Pima County
Battery storage
100 MWWithdrawn / abandoned Pima, AZWest Nov 2022target 2024
Solar + storage project Q459, Maricopa County
Solar + storage
100 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2027
Onshore wind project C1-57, Carbon County
Onshore wind
100 MWWithdrawn / abandoned Carbon, WYWest May 2021target 2025
Onshore wind project GI-0710, Hand County
Onshore wind
100 MWWithdrawn / abandoned Hand, SDWest May 2007target 2009
Battery storage project Company IN, Washoe County
Battery storage
100 MWWithdrawn / abandoned Washoe, NVWest Mar 2018target 2021
Battery storage project 137, Pima County
Battery storage
100 MWWithdrawn / abandoned Pima, AZWest Sep 2022target 2027
Solar project C3-117, Duchesne County
Solar
100 MWWithdrawn / abandoned Duchesne, UTWest May 2023target 2028
Gas project CLPT-G3, Laramie County
Gas
100 MWWithdrawn / abandoned Laramie, WYWest Jul 2011target 2014
Battery storage project Q438, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Sep 2021target 2024
Onshore wind project 17-08211, Larimer County
Onshore wind
100 MWWithdrawn / abandoned Larimer, COWest Aug 2017target 2020
Onshore wind project 2008-G7
Onshore wind
100 MWWithdrawn / abandoned West Feb 2008target 2011
Battery storage project Q74, Los Angeles County
Battery storage
100 MWWithdrawn / abandoned Los Angeles, CAWest Aug 2019target 2022
Battery storage project 89, Thurston County
Battery storage
100 MWWithdrawn / abandoned Thurston, WAWest Aug 2020target 2023
EA100W Project
Onshore wind
100 MWWithdrawn / abandoned Chaves, NMWest Mar 2019target 2021
Battery storage project Company QW, Washoe County
Battery storage
100 MWWithdrawn / abandoned Washoe, NVWest Mar 2024target 2026
Onshore wind project 221-E, Uinta County
Onshore wind
100 MWWithdrawn / abandoned Uinta, WYWest May 2008target 2012
Solar + storage project C2-124, Millard County
Solar + storage
100 MWWithdrawn / abandoned Millard, UTWest May 2022target 2025
Solar + storage project C3-058, Carbon County
Solar + storage
100 MWWithdrawn / abandoned Carbon, UTWest May 2023target 2026
Solar project Q180, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2015
Solar + storage project C3-127, Kane County
Solar + storage
100 MWWithdrawn / abandoned Kane, UTWest May 2023target 2027
Battery storage project GI-2025-11, Mesa County
Battery storage
100 MWWithdrawn / abandoned Mesa, COWest Apr 2025target 2028
Gas project GI-1304, Mckenzie County
Gas
100 MWWithdrawn / abandoned Mckenzie, NDWest Apr 2013target 2016
Solar + storage project 1024, Cache County
Solar + storage
100 MWWithdrawn / abandoned Cache, UTWest May 2018target 2020
Solar project 603, Payette County
Solar
100 MWWithdrawn / abandoned Payette, IDWest May 2021
Onshore wind project 56, Apache County
Onshore wind
99.1 MWWithdrawn / abandoned Apache, AZWest Feb 2017target 2018
Onshore wind project GI-0803, Rolette County
Onshore wind
99.0 MWWithdrawn / abandoned Rolette, NDWest Jan 2008target 2009
Onshore wind project 179, Natrona County
Onshore wind · PacifiCorp Commercial & Trading
99.0 MWWithdrawn / abandoned Natrona, WYWest Jan 2008target 2010
Onshore wind project 184, Albany County
Onshore wind · PacifiCorp Commercial & Trading
99.0 MWWithdrawn / abandoned Albany, WYWest Jan 2008target 2009
Solar project Company 162, Clark County
Solar
99.0 MWWithdrawn / abandoned Clark, NVWest Mar 2018target 2021
Solar project PIS019, Tooele County
Solar · PacifiCorp
99.0 MWWithdrawn / abandoned Tooele, UTWest Jun 2022target 2025
Onshore wind project 181, Natrona County
Onshore wind · PacifiCorp Commercial & Trading
99.0 MWWithdrawn / abandoned Natrona, WYWest Jan 2008target 2011
Onshore wind project GI-0722, Grant County
Onshore wind
99.0 MWWithdrawn / abandoned Grant, SDWest Nov 2007target 2009
Onshore wind project GI-1209, Charles Mix County
Onshore wind · Pioneer Energy
99.0 MWWithdrawn / abandoned Charles Mix, SDWest Jun 2012target 2014
Solar project Q58, Yuma County
Solar
99.0 MWWithdrawn / abandoned Yuma, AZWest Dec 2008target 2017
Onshore wind project GI-1005, Pennington County
Onshore wind
99.0 MWWithdrawn / abandoned Pennington, SDWest Mar 2010target 2012
Onshore wind project 100-B, Big Horn County
Onshore wind · Gaelectric
99.0 MWWithdrawn / abandoned Big Horn, MTWest Nov 2006target 2008
Onshore wind project 100-A, Big Horn County
Onshore wind · Gaelectric
99.0 MWWithdrawn / abandoned Big Horn, MTWest Nov 2006target 2008
Onshore wind project GI-1214, Brown County
Onshore wind · Day County Wind II
99.0 MWWithdrawn / abandoned Brown, SDWest Oct 2012target 2013
Onshore wind project 2008-G3
Onshore wind
99.0 MWWithdrawn / abandoned West Jan 2008target 2010
Onshore wind project 107, Clark County
Onshore wind
99.0 MWWithdrawn / abandoned Clark, SDWest May 2009target 2015
Onshore wind project GI-0917, Stanley County
Onshore wind
99.0 MWWithdrawn / abandoned Stanley, SDWest May 2009target 2011
Page 56 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)