United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2011 requests) โ€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown808106.0 GW
Active in queue4,539 MW21 requests
Agreement signed2,971 MW15 requests
Withdrawn808106.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

808 requests ยท page 5 of 17
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 31, Whitman County
Onshore wind
150 MWWithdrawn / abandoned Whitman, WAWest Feb 2011target 2014
Onshore wind project J218, Adams County
Onshore wind
150 MWWithdrawn / abandoned Adams, NDMISO Jun 2011target 2012
Onshore wind project GEN-2011-042, Barber County
Onshore wind
150 MWWithdrawn / abandoned Barber, KSSPP Sep 2011target 2014
Onshore wind project X3-036, Grant County
Onshore wind
150 MWWithdrawn / abandoned Grant, WVPJM Aug 2011target 2012
Areva Solar Az I
Solar
150 MWWithdrawn / abandoned Yuma, AZCAISO Mar 2011target 2015
Wildflower Green Energy Farm- Solar
Solar
150 MWWithdrawn / abandoned Los Angeles, CACAISO Mar 2011target 2013
Onshore wind project GEN-2011-043, Barber County
Onshore wind
150 MWWithdrawn / abandoned Barber, KSSPP Sep 2011target 2013
Monterey Wind
Onshore wind
150 MWWithdrawn / abandoned Monterey, CACAISO Mar 2011target 2013
Gas project 230, Scott County
Gas
150 MWWithdrawn / abandoned Scott, MSSoutheast Oct 2011
Mule Mountain Solar Project
Solar
150 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2014
Silvertree Greenworks
Solar
150 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2014
Maricopa California Solar Farms I
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Cedar Cap Wind
Onshore wind ยท Gamesa
150 MWWithdrawn / abandoned ERCOT Nov 2011target 2016
Solar project Q201, Maricopa County
Solar
150 MWWithdrawn / abandoned Maricopa, AZWest Jun 2011target 2014
Onshore wind project GEN-2011-041, Barber County
Onshore wind
150 MWWithdrawn / abandoned Barber, KSSPP Sep 2011target 2013
Onshore wind project GEN-2011-044, Barber County
Onshore wind
150 MWWithdrawn / abandoned Barber, KSSPP Sep 2011target 2014
Solar project Company 113, Clark County
Solar
150 MWWithdrawn / abandoned Clark, NVWest Nov 2011target 2015
Gas project X3-006, Berks County
Gas
150 MWWithdrawn / abandoned Berks, PAPJM Aug 2011target 2014
Onshore wind project X2-058, Hancock County
Onshore wind
150 MWWithdrawn / abandoned Hancock, OHPJM Jun 2011target 2012
Solar project Q20, Inyo County
Solar
138 MWWithdrawn / abandoned Inyo, CAWest Oct 2011target 2014
Gas project X1-080, Prince George County
Gas
135 MWWithdrawn / abandoned Prince George, VAPJM Apr 2011target 2015
Whitehorse Mountain Wind Power Plant
Onshore wind
132 MWWithdrawn / abandoned Siskiyou, CACAISO Nov 2011target 2016
Onshore wind project J197, Lenawee County
Onshore wind
125 MWWithdrawn / abandoned Lenawee, MIMISO Feb 2011target 2013
Great Valley Solar
Solar
120 MWWithdrawn / abandoned Tulare, CACAISO Mar 2011target 2013
Onshore wind project J199, Gratiot County
Onshore wind
120 MWWithdrawn / abandoned Gratiot, MIMISO Feb 2011target 2013
Adame 1
Solar
118 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2014
SSE phase 1
Onshore wind ยท Spinning Star Energy LLC
113 MWWithdrawn / abandoned ERCOT Jul 2011target 2050
Miami Wind G3
Onshore wind ยท Invenergy
111 MWWithdrawn / abandoned ERCOT Jun 2011target 2016
Westside Renewal PV Project
Solar
110 MWWithdrawn / abandoned Kings, CACAISO Mar 2011target 2014
Gas project X4-018, Hudson County
Gas
110 MWWithdrawn / abandoned Hudson, NJPJM Nov 2011target 2015
Onshore wind project GEN-2011-012, Sherman County
Onshore wind
105 MWWithdrawn / abandoned Sherman, TXSPP Mar 2011target 2012
Onshore wind project GEN-2011-051, Dewey County
Onshore wind
104 MWWithdrawn / abandoned Dewey, OKSPP Sep 20112017
Onshore wind project GEN-2011-013, Murray County
Onshore wind
102 MWWithdrawn / abandoned Murray, OKSPP Mar 2011target 2012
Onshore wind project G0467, Wasco County
Onshore wind
101 MWWithdrawn / abandoned Wasco, ORWest Oct 2011target 2015
West Ranch Solar
Solar ยท Pristine Sun
100 MWWithdrawn / abandoned ERCOT Jun 2011target 2018
Royal Solar Project
Solar
100 MWWithdrawn / abandoned Los Angeles, CACAISO Mar 2011target 2018
Solar project 369, Iron County
Solar
100 MWWithdrawn / abandoned Iron, UTWest Feb 2011target 2013
Onshore wind project J225, Eaton County
Onshore wind
100 MWWithdrawn / abandoned Eaton, MIMISO Sep 2011target 2012
Sandy Hills Solar
Solar ยท SunPower
100 MWWithdrawn / abandoned ERCOT Mar 2011target 2017
Desert Harvest Solar Farm
Solar
100 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2015
Enrico Matson III
Solar
100 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2015
Csed Barstow Road 100 MW PV Generating Station
Solar
100 MWWithdrawn / abandoned San Bernardino, CACAISO Mar 2011target 2014
Solar project Q183, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2014
Solar project Q179, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2014
Solar project J207, Washtenaw County
Solar
100 MWWithdrawn / abandoned Washtenaw, MIMISO Mar 2011target 2013
Bellota Solar Farm
Solar
100 MWWithdrawn / abandoned San Joaquin, CACAISO Mar 2011target 2014
Onshore wind project X2-039, Ashland County
Onshore wind
100 MWWithdrawn / abandoned Ashland, OHPJM Jun 2011target 2013
Solar project X3-022, Adams County
Solar
100 MWWithdrawn / abandoned Adams, PAPJM Aug 2011target 2014
Onshore wind project GEN-2008-105, Noble County
Onshore wind
100 MWWithdrawn / abandoned Noble, OKSPP Sep 2011target 2011
San Joaquin Solar
Solar
100 MWWithdrawn / abandoned San Joaquin, CACAISO Mar 2011target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)