πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Cedar Cap Wind

Cedar Cap Wind is a 150 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2011 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
14INR0020
Grid region
ERCOT (Texas)
Developer
Gamesa
Connection point (POI)
Tule Canyon 345kV (79503)
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
10 November 2011
Proposed online date
October 2016

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem