Desert Harvest Solar Farm

Desert Harvest Solar Farm is a 100 MW solar request withdrawn in the CAISO interconnection queue, in Imperial County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
839
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Colorado River Substation 230kV bus
Location
Imperial County, California
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
November 2015
Withdrawn
March 2012

Location

Marker shows the centre of Imperial County; the queue data does not give exact sites.