πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J207, Washtenaw County

Solar project J207, Washtenaw County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Washtenaw County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedJun 2012 (project stopped here)
  3. ConsentedJun 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J207
Grid region
MISO (Midcontinent)
Connection point (POI)
Luzon - Kentucky 120 kV
Location
Washtenaw County, Michigan
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
1 March 2011
Agreement signed
27 June 2012
Proposed online date
March 2013
Withdrawn
June 2012

Location

Marker shows the centre of Washtenaw County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Washtenaw County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem