πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR Β· WEST

Solar project Q179, San Juan County

Solar project Q179, San Juan County is a 100 MW solar request withdrawn in the West interconnection queue, in San Juan County, New Mexico, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2011 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q179
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Four Corners 230kV substation
Location
San Juan County, New Mexico
Technology
Solar: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
12 January 2011
Proposed online date
June 2014

Location

Marker shows the centre of San Juan County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in San Juan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem