United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESProjects with signed interconnection agreements in the USA (2021 requests) — page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Camp Creek Solar SLF Solar + storage · White Rock Solar, LLC |
110 MW | Agreement signed |
| Solar project 482, Cumberland County Solar |
110 MW | Agreement signed |
| Third Coast BESS Battery storage · Third Coast BESS LLC |
103 MW | Agreement signed |
| Louisa Energy Storage Battery storage · VESI 49 LLC |
103 MW | Agreement signed |
| Oakdale Storage Battery storage |
103 MW | Agreement signed |
| Seven Flags BESS Battery storage · Seven Flags BESS LLC |
103 MW | Agreement signed |
| Tierra Seca BESS Battery storage · Tierra Seca BESS LLC |
103 MW | Agreement signed |
| Bexar ESS Battery storage · Bexar ESS LLC |
103 MW | Agreement signed |
| Los Nietos Battery storage |
102 MW | Agreement signed |
| Tokay Storage Battery storage |
102 MW | Agreement signed |
| Broadleaf Solar Solar |
101 MW | Agreement signed |
| Double Springs Energy Storage Battery storage |
101 MW | Agreement signed |
| Sunbeam Storage Battery storage |
101 MW | Agreement signed |
| Paradiso BESS Battery storage · VESI 13 |
101 MW | Agreement signed |
| Hermes Solar Solar + storage · Bell 1 Solar, LLC |
100 MW | Agreement signed |
| Peaceful Hollow BESS Battery storage |
100 MW | Agreement signed |
| Solar + storage project 604, Elmore County Solar + storage · Crimson Orchard Solar LLC |
100 MW | Agreement signed |
| Battery storage project GEN-2021-041, Canadian County Battery storage |
100 MW | Agreement signed |
| Midpoint Solar Solar · Midpoint Solar, LLC |
98.3 MW | Agreement signed |
| Onshore wind project GI-96, Lincoln County Onshore wind |
97.5 MW | Agreement signed |
| Rocinante Solar Solar + storage · Brush Country Solar Project, LLC |
95.3 MW | Agreement signed |
| High Noon Storage Solar + storage · High Noon Solar Project, LLC |
94.0 MW | Agreement signed |
| Solar project J1827, Morehouse Parish County Solar |
90.0 MW | Agreement signed |
| Payne Battlecreek Solar · Gransolar Texas Ten, LLC |
85.0 MW | Agreement signed |
| Solar project BHBE G15, Meade County Solar · Vedauwoo Holdings Black Hills 1 LLC |
80.0 MW | Agreement signed |
| Gaia Storage Solar + storage · Gaia Solar, LLC |
78.8 MW | Agreement signed |
| Eagle Springs Solar Solar + storage · Eagle Springs Solar, LLC |
77.2 MW | Agreement signed |
| Battery storage project GEN-2021-052, Muskogee County Battery storage |
75.0 MW | Agreement signed |
| Solar project J1561, Acadia Parish County Solar |
75.0 MW | Agreement signed |
| Battery storage project GEN-2021-048, Lancaster County Battery storage |
75.0 MW | Agreement signed |
| Battery storage project GEN-2021-019, Noble County Battery storage |
74.9 MW | Agreement signed |
| Solar + storage project 425, Bradford County Solar + storage · Third Party |
74.9 MW | Agreement signed |
| Blue Jay Solar II Solar · Blue Jay Solar I, LLC |
69.0 MW | Agreement signed |
| Starling Storage Solar + storage · Starling Storage, LLC |
63.6 MW | Agreement signed |
| Honeycomb Solar SLF Solar + storage · Honeycomb Solar, LLC |
61.4 MW | Agreement signed |
| Orange Grove BESS Solar + storage · Talitha Energy Project, LLC |
61.4 MW | Agreement signed |
| Bird Dog Energy Storage Battery storage · VESI 37 LLC |
60.4 MW | Agreement signed |
| Oriana BESS Solar + storage · Oriana Solar LLC |
60.3 MW | Agreement signed |
| Solar + storage project Company 193, Clark County Solar + storage |
57.0 MW | Agreement signed |
| Bynum Solar Project Solar · Bynum Solar Project, LLC |
56.0 MW | Agreement signed |
| Orleans Solar + storage |
51.1 MW | Agreement signed |
| Lumberjack Storage Battery storage · EDP Renewables North America LLC |
50.9 MW | Agreement signed |
| Midpoint Storage Battery storage · Midpoint Solar, LLC |
50.9 MW | Agreement signed |
| Husky Solar Solar |
50.2 MW | Agreement signed |
| Zinnia Storage Battery storage |
50.0 MW | Agreement signed |
| Battery storage project GEN-2021-042, Jackson County Battery storage |
50.0 MW | Agreement signed |
| Limewood Storage Solar + storage · Limewood Bell Renewables LLC |
50.0 MW | Agreement signed |
| Gas project GI-2021-2, Weld County Gas |
49.0 MW | Agreement signed |
| Solar project GEN-2021-SR8, Harper County Solar |
42.0 MW | Agreement signed |
| Geothermal project Company LT, Lander County Geothermal |
40.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)68 · 35.4 GW
- ERCOT (Texas)91 · 16.3 GW
- West (non-ISO utilities)55 · 11.7 GW
- ISO-NE (New England)17 · 3,473 MW
- SPP (Southwest Power Pool)19 · 3,459 MW
- Southeast (non-ISO utilities)12 · 1,908 MW
- MISO (Midcontinent)8 · 1,055 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)