United States › Grid › Interconnection queues › Minnesota

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Minnesota — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown48280.5 GW
Active in queue28.4 GW155 requests
Agreement signed309 MW9 requests
Withdrawn48280.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

482 requests · page 5 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J4060, Mcleod County
Battery storage
129 MWWithdrawn / abandoned Mcleod, MNMISO Aug 2025target 2030
Solar project J1057, Jackson County
Solar
125 MWWithdrawn / abandoned Jackson, MNMISO Mar 2018target 2021
Solar project J2863, Fillmore County
Solar
125 MWWithdrawn / abandoned Fillmore, MNMISO Sep 2022target 2027
Solar project J1086, Nobles County
Solar
120 MWWithdrawn / abandoned Nobles, MNMISO Mar 2018target 2021
Onshore wind project J1487, Freeborn County
Onshore wind
120 MWWithdrawn / abandoned Freeborn, MNMISO Apr 2019target 2021
Coal project G169, Sherburne County
Coal
120 MWWithdrawn / abandoned Sherburne, MNMISO Jan 2002
Solar project J1300, Nobles County
Solar
120 MWWithdrawn / abandoned Nobles, MNMISO Apr 2019target 2021
Onshore wind project J414, Freeborn County
Onshore wind
120 MWWithdrawn / abandoned Freeborn, MNMISO Nov 2014target 2019
Solar project J2030, Isanti County
Solar
120 MWWithdrawn / abandoned Isanti, MNMISO Jul 2021target 2024
Onshore wind project G600, Marshall County
Onshore wind
110 MWWithdrawn / abandoned Marshall, MNMISO Feb 2006target 2010
Onshore wind project J785, Jackson County
Onshore wind
105 MWWithdrawn / abandoned Jackson, MNMISO Jun 2017target 2021
Onshore wind project J556, Renville County
Onshore wind
102 MWWithdrawn / abandoned Renville, MNMISO Apr 2016target 2019
Onshore wind project J306, Traverse County
Onshore wind
101 MWWithdrawn / abandoned Traverse, MNMISO Nov 2013target 2016
Gas project G390, Sherburne County
Gas
100 MWWithdrawn / abandoned Sherburne, MNMISO Nov 2003target 2012
Onshore wind project J140, Fillmore County
Onshore wind
100 MWWithdrawn / abandoned Fillmore, MNMISO Nov 2009target 2010
Onshore wind project J596, Big Stone County
Onshore wind
100 MWWithdrawn / abandoned Big Stone, MNMISO May 2016target 2018
Onshore wind project J520, Pipestone County
Onshore wind
100 MWWithdrawn / abandoned Pipestone, MNMISO Nov 2015target 2017
Onshore wind project G593, Jackson County
Onshore wind
100 MWWithdrawn / abandoned Jackson, MNMISO Feb 2006target 2007
Solar project J702, Wadena County
Solar
100 MWWithdrawn / abandoned Wadena, MNMISO Sep 2016target 2018
Solar project J1143, Morrison County
Solar
100 MWWithdrawn / abandoned Morrison, MNMISO Mar 2018target 2020
Battery storage project J3312, Washington County
Battery storage
100 MWWithdrawn / abandoned Washington, MNMISO Apr 2024target 2028
Onshore wind project H017, Cottonwood County
Onshore wind
100 MWWithdrawn / abandoned Cottonwood, MNMISO Apr 2008target 2009
Battery storage project J1468, Dakota County
Battery storage
100 MWWithdrawn / abandoned Dakota, MNMISO Apr 2019target 2022
Battery storage project J3665, Redwood County
Battery storage
100 MWWithdrawn / abandoned Redwood, MNMISO Apr 2024target 2028
Other project G247, Mower County
Other
100 MWWithdrawn / abandoned Mower, MNMISO Aug 2002target 2003
Onshore wind project J2092, Wright County
Onshore wind
100 MWWithdrawn / abandoned Wright, MNMISO Aug 2021target 2025
Onshore wind project J575, Lincoln County
Onshore wind
100 MWWithdrawn / abandoned Lincoln, MNMISO May 2016target 2018
Onshore wind project J184, Rock County
Onshore wind
100 MWWithdrawn / abandoned Rock, MNMISO Nov 2010
Onshore wind project J745, Nobles County
Onshore wind
100 MWWithdrawn / abandoned Nobles, MNMISO Nov 2016target 2021
Onshore wind project G668, Big Stone County
Onshore wind
100 MWWithdrawn / abandoned Big Stone, MNMISO Aug 2006target 2009
Onshore wind project J015, Goodhue County
Onshore wind
100 MWWithdrawn / abandoned Goodhue, MNMISO Jan 2009target 2012
Onshore wind project J958, Lincoln County
Onshore wind
100 MWWithdrawn / abandoned Lincoln, MNMISO Mar 2018target 2020
Onshore wind project J137, Mower County
Onshore wind
100 MWWithdrawn / abandoned Mower, MNMISO Feb 2009target 2009
Onshore wind project G269, Mower County
Onshore wind
100 MWWithdrawn / abandoned Mower, MNMISO Nov 2002target 2005
Onshore wind project G737, Stevens County
Onshore wind
100 MWWithdrawn / abandoned Stevens, MNMISO Feb 2007target 2008
Solar project J349, Sherburne County
Solar
100 MWWithdrawn / abandoned Sherburne, MNMISO May 2014target 2016
Onshore wind project G968, Marshall County
Onshore wind
100 MWWithdrawn / abandoned Marshall, MNMISO Jan 2008target 2010
Solar project J735, Morrison County
Solar
100 MWWithdrawn / abandoned Morrison, MNMISO Nov 2016target 2019
Onshore wind project J019, Douglas County
Onshore wind
100 MWWithdrawn / abandoned Douglas, MNMISO Jan 2009target 2012
Onshore wind project G770, Martin County
Onshore wind
100 MWWithdrawn / abandoned Martin, MNMISO Mar 2007target 2008
Onshore wind project H073, Douglas County
Onshore wind
100 MWWithdrawn / abandoned Douglas, MNMISO Jun 2008target 2011
Onshore wind project J086, Kandiyohi County
Onshore wind
100 MWWithdrawn / abandoned Kandiyohi, MNMISO Oct 2009target 2012
Other project G244, Mower County
Other
100 MWWithdrawn / abandoned Mower, MNMISO Aug 2002target 2005
Onshore wind project J577, Pipestone County
Onshore wind
100 MWWithdrawn / abandoned Pipestone, MNMISO May 2016target 2018
Battery storage project J3807, Goodhue County
Battery storage
100 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2024target 2028
Onshore wind project G555, Stevens County
Onshore wind
100 MWWithdrawn / abandoned Stevens, MNMISO Oct 2005target 2006
Other project G246, Mower County
Other
100 MWWithdrawn / abandoned Mower, MNMISO Aug 2002target 2003
Solar project J326, Chisago County
Solar
100 MWWithdrawn / abandoned Chisago, MNMISO Mar 2014target 2016
Onshore wind project J927, Faribault County
Onshore wind
100 MWWithdrawn / abandoned Faribault, MNMISO Jun 2017target 2021
Onshore wind project J064, Beltrami County
Onshore wind
100 MWWithdrawn / abandoned Beltrami, MNMISO Aug 2009target 2011
Page 5 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)